Merrimack Valley Metropolitan Planning
Organization
Federal Fiscal Years 2022 to 2026
Transportation Improvement Program
Final Report
May 2021
Prepared by the Merrimack Valley Planning Commission
This document was prepared in cooperation with the Massachusetts Department of Transportation and the U.S. Department of Transportation. (under Contract # 112304 with MassDOT) The views and opinions of the Merrimack Valley Planning Commission expressed herein do not necessarily state or reflect those of the Massachusetts Department of Transportation or the U.S. Department of Transportation.
Page intentionally left blank.
Table of Contents
Title VI Notice to Beneficiaries
Endorsement Page for Federal TIP Signatures
Certification of the Merrimack Valley MPO Transportation Planning Process
310 CMR 60.05: Global Warming Solutions Act Signatures
Part A. 1. TIP Development Process
Part A. 2. Performance Measures
Part A. 4. Public Participation
Public Participation Plan Stakeholder List
Part A. 5. Amendment/ Adjustment Procedures
Part A. 6. High Priority Projects
Part A. 7. Advance Construction
Part A. 8. Transportation Funding Programs
Organization of Project Listings Highway Projects
Summary of Highway Project Listings by Town
Part C.1. Highway Program Financial Plan
Highway Program Financial Plan Table
Summary of Highway Funding Categories
Part C. 2. Transit Program Financial Plan
Transit Program Financial Plan Table
Summary of Transit Funding Categories
MVRTA Transit Operations and Maintenance Summary Table
Part C. 3. Status on Implementation of FFY 2021 TIP Projects
Part C. 4. Air Quality Conformity
Part C. 5. Special Efforts-ADA
Part C. 6. Title VI Notice to Beneficiaries
Part C. 7. Environmental Justice
Appendix60
Page intentionally left blank.
The Merrimack Valley Planning Commission (MVPC) operates its programs, services and activities in compliance with federal nondiscrimination laws including Title VI of the Civil Rights Act of 1964 (Title VI), the Civil Rights Restoration Act of 1987, and related statutes and regulations. Title VI prohibits discrimination in federally assisted programs and requires that no person in the United States of America shall, on the grounds of race, color or national origin (including limited English proficiency) be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity receiving federal assistance. Related federal nondiscrimination laws administrated by the Federal Highway Administration, the Federal Transit Administration, or both, prohibit discrimination on the basis of age, sex and disability. These protected categories are contemplated within MVPCs Title VI Program consistent with federal interpretation and administration. Additionally, MVPC provides meaningful access to its programs, services, and activities to individuals with limited English proficiency, in compliance with U.S. Department of Transportation policy and guidance on federal Executive Order 13166.
MVPC also complies with the Massachusetts Public Accommodation Law, M.G.L. Chapter 272, Sections 92a, 98, and 98a prohibiting making any distinction, discrimination, or restriction in admission to or treatment in a place of public accommodation based upon race, color, religious creed, national origin, sex, sexual orientation, disability, or ancestry. Likewise, MVPC complies with the Governors Executive Order 526, Section 4 requiring that all of its programs, activities, and services provided, performed, licensed, chartered, funded, regulated, or contracted for shall be conducted without unlawful discrimination based upon race, color, age, gender, ethnicity, sexual orientation, gender identity or expression, religion, creed, ancestry, national origin, disability, veterans status (including Vietnam-era veterans), or background.
Additional Information
To request additional information regarding Title VI and related federal and state nondiscrimination obligations, please contact:
Title VI Program Coordinator
Merrimack Valley Metropolitan Planning Organization
c/o Merrimack Valley Planning Commission
160 Main Street
Haverhill, MA 01830-5061
(978) 374-0519, extension 15
Complaint Filing
To file a complaint alleging a violation of Title VI or related federal nondiscrimination law, contact the Title VI Program Coordinator (above) within one hundred and eighty (180) days of the alleged discriminatory conduct.
To file a complaint alleging a violation of the Commonwealths Public Accommodation Law, contact the Massachusetts Commission Against Discrimination within three hundred (300) days of the alleged discriminatory conduct at:
Massachusetts Commission Against Discrimination (MCAD)
One Ashburton Place, 6th Floor
Boston, MA 02109
(617) 994-6000
TTY: (617) 994-6196
Page intentionally left blank.
Page intentionally left blank.
Page intentionally left blank.
Merrimack Valley Metropolitan Planning Organization
FFYs 2022 to 2026 Transportation Improvement Program
Final Report prepared May 2021
Federal transportation authorization legislation establishes funding categories for transportation projects that may be eligible for Federal funding and sets maximum funding levels per category for each year of the legislation. Projects in this TIP are planned to be primarily funded through the federal transportation act titled Fixing Americas Surface Transportation Act (FAST Act) that was signed into law December 4, 2015. The FAST Act funds $305 billion dollars for transportation for Federal Fiscal Years (FFYs) 2016 through 2020. This funding has been extended through September 30, 2021 by a continuing resolution that extends current surface transportation funding reauthorization.
The previous legislation Moving Ahead for Progress in the 21st Century (MAP-21) established planning factors known as the MAP-21 eight planning factors. The FAST Act adds two new planning factors (I and J in the list that follows), the FAST Act stipulates that the metropolitan planning process...
provide for consideration of projects and strategies that will-
A) support the economic vitality of the metropolitan area, especially by enabling global competitiveness, productivity and efficiency;
B) increase the safety of the transportation system for motorized and non-motorized users;
C) increase the security of the transportation system for motorized and non-motorized users;
D) increase the accessibility and mobility of people and for freight;
E) protect and enhance the environment, promote energy conservation, improve quality of life, and promote consistency between transportation improvements and State and local planned growth and economic development patterns;
F) enhance the integration and connectivity of the transportation system, across and between modes, for people and freight;
G) promote efficient system management and operation;
H) emphasize the preservation of the existing transportation system;
I) improve the resiliency and reliability of the transportation system and reduce or mitigate stormwater impacts of surface transportation; and
J) enhance travel and tourism.
It is the responsibility of the Federal mandated, State designated, regional Metropolitan Planning Organizations (MPOs) to carry out the Federal transportation planning process in their respective urbanized areas and prepare many Federal transportation documents, including the Transportation Improvement Program (TIP). This process, and the MPOs themselves, were established with the intention to include local and regional input into the Federal transportation planning process.
Based on Federal regulations any transportation project funded through the Federal Highway Administration (FHWA), or the Federal Transit Administration (FTA) must be listed in the appropriate regions Transportation Improvement Program (TIP). MassDOT combines the 13 regional MPO TIPs with statewide projects to produce the Statewide TIP (STIP) from which Federal-aid highway and transit projects are chosen. Without such a listing, Federal Highway funds cannot be expended by the Massachusetts Department of Transportation (MassDOT) on local or State projects. Similarly, the Merrimack Valley Regional Transit Authority (MVRTA) can only receive federal funds for projects listed in the TIP and STIP.
Merrimack Valley Metropolitan Planning Organization (MVMPO)
The MVMPO was first created by the Governor of Massachusetts in 1972. The MVMPO covers the same 15-community geographic area that defines the MVPC region and the MVRTA service area. The current MVMPO membership is as follows:
Acting Secretary of MassDOT Jamey L. Tesler
MassDOT Highway Division Administrator Jonathan L. Gulliver
Merrimack Valley Planning Commission (MVPC) Acting Director Anthony Komornick
Administrator/CEO Merrimack Valley Regional Transit Authority Joseph Costanzo
Mayor of Haverhill James Fiorentini
Mayor of Lawrence Kendrys Vasquez
Representing Region 1 (Amesbury, Newburyport, Salisbury) Neil Harrington
Representing Region 2 (Newbury, Rowley, West Newbury) Robert Snow
Representing Region 3 (Boxford, Georgetown, Groveland, Merrimac) John Cashell
Representing Region 4 (Andover, Methuen, North Andover) Paul Materazzo
Ex officio, non-voting members of the MVMPO include:
Federal Highway Administration Massachusetts Division Jeff McEwen
Federal Transit Administration Region I Peter Butler
Rockingham Planning Commission MPO (NH), Chairman RPC Richard McDermott
Boston MPO, President MAPC Erin Wortman
Northern Middlesex MPO, Chairman NMCOG Andrew Deslaurier
Nashua MPO (NH), Chairman NRPC Susan Ruch
The TIP has been prepared in accordance with 23 CFR 450.326.
The development of the TIP starts with the Regional Transportation Plan (RTP). The MVMPOs RTP is a twenty-year plan for transportation projects that can be programmed for implementation with Federal funds. The RTP is fiscally constrained and lists potential future projects in five-year blocks. Projects were chosen for the RTP based on MAP-21 transportation planning factors, meeting performance measure targets, existing roadway conditions, problems identified through ongoing pavement, congestion, and safety analyses conducted by the MVMPO, local and state project priorities and fiscal factors. Each year, the MVMPO programs projects from the RTP that are ready-to-go into its five-year Transportation Improvement Program (TIP). Only those projects that are specifically identified in the RTP, or are consistent with its recommendations, can be programmed in the TIP. The planning tasks conducted in developing the RTP and the TIP are included in the regions Unified Planning Work Program (UPWP) which is produced for public review annually. The UPWP includes additional transportation planning activities such as intersection and roadway analyses and studies.
Only projects from the RTP first two time bands of years (i.e., 2020 to 2024 and 2025 to 2029) are programmed in the TIP. An inconsistency with spending shown in the RTP is that when the MVMPOs FFY 2020 RTP was developed, it was assumed the construction of North Avenue in Haverhill would occur in the FFYs 2020 to 2024 time-band. The estimated project cost for this project and for the North Andover Route 114 project have increased significantly to the point where programming both of these projects in the 2022 to 2026 TIP is not financially feasible. Neither project would be ready to advertise until 2024 or later. The Route 114 project has a TEC score of 12.12, the Haverhill North Avenue project has a TEC score of 8.58. In addition, the North Andover Route 114 project is further along in the design process, therefore the North Andover Route 114 project is programmed to start in FFY 2024 and then consumes all the regional target funding in FFYs 2025 and 2026 and will also need all of the FFY 2027 funding before funding may be available for Haverhill North Avenue. Also two sections of the Border-to-Boston Rail Trail, Georgetown-Boxford from Georgetown Road to West Main Street and Georgetown-Newbury Northern Georgetown to Byfield, were slated for 2020 to 2024, are programmed for Statewide funding in 2025.
Bicycle and pedestrian paths and accomodations on roadways and bridges are part of the Massachusetts 2019 Statewide Pedestrian Transportation Plan and 2019 Statewide Bicycle Transportation Plan which strive to consider pedestrians and bicyclists at the same level of importance as drivers in planning, design and maintenance including incorporating the safety of these users in projects. These Plans also conduct analyses which locate areas with Potential for Everyday Biking, Gaps in the High Comfort Bikeway Network, Potential for Walkable Trips, Transit Route, and High Pedestrian and Bicycle Crash locations used to initiate projects as well as score projects for the Massachusetts Capital Investment Plan (CIP). All TIP projects are part of the (CIP) which has a category of Expansion Projects which include projects that expand bicycle and pedestrian networks to provide more transportation options and address health and sustainability objectives. Many bicycle and pedestrian projects are initiated by a municipality because the State provides funding for these projects in the Complete Streets, Shared Use Path, and the Safe Route to Schools Programs.
Federal legislation requires states to develop a Transportation Asset Management Plan (TAMP) that includes Performance Measures for NHS roadways and bridges as part of the asset management process. MassDOT Highway Division submitted an initial TAMP to FHWA on April 30, 2018, the TAMP was finalized in September of 2019.
The PM1 HSIP and Safety Performance Measures apply to all public roads. The PM2 Pavement and Bridge Performance Measures apply only to NHS (National Highway System) roads and bridges. PM3 Performance Measures apply to various facilities as defined below.
MassDOT has established targets based on these performance measures and the MPOs have worked with MassDOT in either a) choosing the same targets, b) adapting them to the specific region, or c) choosing new targets as goals for the MPO. The MVMPO has adopted all of the targets established by MassDOT. MassDOT and the MPOs will work cooperatively to exchange data and performance targets and measures as required by the legislation.
MassDOTs Tracker https://www.massdottracker.com/wp/ contains annual performance management reports. These performance targets and corresponding actuals are contained in the reports.
The following are the performance measures, divided into three categories, as defined by the Final Federal Rules:
HSIP and Safety Performance Management Measures to be applied to all public roads (PM1):
� Number of Fatalities
� Fatality rate per 100 million vehicle-miles traveled
� Number of Serious Injuries
� Serious injury rate per 100 million vehicle-miles traveled
� Number of non-motorized fatalities and non-motorized serious injuries
Pavement and Bridge Condition Performance Measures (PM2):
� Percentage of Pavements of the Interstate System in Good condition
� Percentage of Pavements of the Interstate System in Poor condition
� Percentage of Pavements of the non-Interstate NHS in Good condition
� Percentage of Pavements of the non-Interstate NHS in Poor condition
� Percentage of NHS bridges by deck area classified as in Good condition
� Percentage of NHS bridges by deck area classified as in Poor condition
MassDOT has submitted a draft NHS Transportation Asset Management Plan (TAMP), as required by MAP-21, to address pavement and bridge conditions on the NHS system. The TAMP was finalized in September 2019.
System Performance/ Freight/ CMAQ Performance Measures (PM3):
� Percent of the Person-Miles Traveled on the Interstate that are Reliable
� Percent of the Person-Miles Traveled on the non-Interstate NHS that are Reliable
� Truck Travel Time Reliability (TTTR) Index on the Interstate System
� Annual Hours of Peak Hour Excessive Delay Per Capita
� Percent of Non-SOV Travel on the NHS System
� Total Emission Reduction of all projects funded with CMAQ in areas designated as nonattainment or maintenance for ozone (O3), carbon monoxide (CO), or particulate matter (PM10 and PM2.5)
MassDOT collects data for and establishes targets for each of the performance measures and presents these to the MPO. The MVMPO then votes on whether to adopt the MassDOT targets, or establish their own. Projects are programmed for funding with consideration of meeting the targets established for each measure. The performance measures are incorporated into the Transportation Improvement Program (TIP) Transportation Evaluation Criteria (TEC) in the scoring categories as indicated in the TEC Scoring Criteria Chart in Section A.3. of the TIP.
Targets are set by examining historic trends in the data and considering future plans for potential improvements.
Safety Performance Measures (PM1)
The Merrimack Valley MPO at its January 2021 meeting chose to adopt the statewide safety performance measure targets set by MassDOT for Calendar Year (CY) 2021. In setting these targets, MassDOT has followed FHWA guidelines by using statewide crash data and Highway Performance Monitoring System (HPMS) data for vehicle miles traveled (VMT) in order to calculate 5 year, rolling average trend lines for all FHWA-defined safety measures. Figures 1 to 6 on the following pages illustrate the 5-Year rolling averages and rates discussed below.
Total Fatalities: Per guidance from the Federal Highway Administration (FHWA), MassDOTs 2021 safety target setting process began with a trend line projection based on the most recent available Statewide data (up to 2018). The calendar year (CY) 2021 target of 339 was set to reflect an anticipated decrease in fatalities due to joint initiatives across MassDOT related to sustainable transportation; commitment to several FHWA Every Day Counts (EDC) initiatives (e.g. reducing rural roadway departures); and strategies and legislative proposals that were part of the 2018 Strategic Highway Safety Plan (SHSP), such as the primary seat belt and hands-free driving laws.
The Merrimack Valley Region number of fatalities averaged over the five years from 2015 to 2019 is 18, an increase of 1 over the previous 2014 to 2018 average which was 17.
Fatality Rate: The CY 2021 target of .55 fatalities per 100 million vehicle miles traveled (VMT) Statewide reflects an overall reduction from previous years. It should be noted that MassDOTs long-term goal is to move towards zero deaths.
The Merrimack Valley Region fatality rate increased from 0.4 fatalities per 100 million Vehicle Miles Travelled (VMT) averaged over 2014 to 2018 to 0.48 averaged from 2015 to 2018, but is below the Statewide rate of 0.56 fatalities per 100 million VMT from 2015 to 2018.
Total Serious Injuries: It is anticipated that there will be an overall decrease in the number of serious injuries Statewide due to a continual downward trend line as well as the implementation of countermeasures that are being developed as part of the 2018 Strategic Highway Safety Plan (SHSP). The CY 2021 target of 2,580 was set to reflect this trend. For this performance measure, it is important to note that on January 1st, 2019, Massachusetts moved from the term incapacitating injuries to serious injuries, per federal requirements.
The Merrimack Valley Region Total Serious Injuries increased from 141 averaged from 2014 to 2018 to 147 serious injuries averaged from 2015 to 2019.
Serious Injuries Rate: Similar to the fatality rate, it is anticipated that the downward trend line will result in a drop in the rate of serious injuries from 4.35 per 100 million VMT between 2016 to 2020 to 4.23 between 2017 to 2021 Statewide.
The Merrimack Valley Serious Injury Rate per 100 million VMT increased from 3.8 averaged over 2014 to 2018 to 3.94 from 2015 to 2019, but remains lower than the State average of 4.37 from 2015 to 2019.
Total Number of Non-Motorized Fatalities and Serious Injuries: The most recent data for non-motorized fatalities and serious injuries indicates that the previously increasing trend decreased in 2017, and has continued to decrease since then. The CY 2021 Statewide target has been set to reflect continued projected reductions in non-motorized fatalities and injuries due to a number of multi-disciplinary and multi-agency implementation strategies contained within the Statewide Bike Plan, Statewide Pedestrian Plan, and Strategic Highway Safety Plan.
It is important to note that in prior years, only bicyclist and pedestrian data were used to calculate this target. More recently, it was determined that this category would include other non-motorists. In addition to bicyclists and pedestrians, this category includes skaters and users of wheelchairs and other mobility devices. The historical data within the graph below includes these additional users.
In the Merrimack Valley Region the total number of non-motorized fatalities and serious injuries has increased in the most recent 5-year periods to 22 for the 2014 to 2018 five year average for the 2015 to 2019. The total number of non-motorized fatalities and serious injuries was19 from 2013 to 2017 and from 2012 to 2016.
In recent years, MassDOT and the Merrimack Valley MPO have invested in complete streets, bicycle and pedestrian infrastructure, intersection and safety improvements in both the Capital Investment Plan (CIP) and Statewide Transportation Improvement Program (STIP) to address increasing mode share and to incorporate safety mitigation elements into projects. Moving forward, Merrimack Valley MPO, alongside MassDOT, is actively seeking to improve data collection and methodology for bicycle and pedestrian VMT counts and to continue analyzing crash clusters and crash counts that include both motorized and non-motorized modes in order to address safety issues at these locations.
Bridge & Pavement Performance Measures (PM 2)
The Merrimack Valley MPO has chosen to adopt the 2-year (2020) and 4-year (2022) statewide bridge and pavement performance measure targets set by MassDOT. MassDOT was required to adopt a statewide target by May 20th, 2018, with MPOs either adopting the statewide target or establishing their own by November 2018. In setting these targets, MassDOT has followed FHWA guidelines by measuring bridges and pavement condition using the 9-point National Bridge Inventory Standards (NBIS); the International Roughness Index (IRI); the presence of pavement rutting; and the presence of pavement cracking. 2-year and 4-year targets were set for six individual performance measures: percent of bridges in good condition; percent of bridges in poor condition; percent of Interstate pavement in good condition; percent of Interstate pavement in poor condition; percent of non-Interstate pavement in good condition; and percent of non-Interstate pavement in poor condition. All of the above performance measures are tracked in greater detail in MassDOTs Transportation Asset Management Plan (TAMP), which was finalized in September 2019. It is posted here: https://www.mass.gov/service-details/massdot-asset-management.
Targets for bridge-related performance measures were determined by identifying which bridge projects are programmed and projecting at what rate bridge conditions deteriorate. The bridge-related performance measures measure the percentage of deck area, rather than the total number of bridges.
Performance targets for pavement-related performance measures were based on a single year of data collection, and thus were set to remain steady under the guidance of FHWA. These baseline measures were revisited at the 2-year mark (2020) and reported by MassDOT in the 2020 Mid-performance report. (See table on next page.) The decision was made in the Mid-performance report to keep the pavement condition targets the same.
MassDOT continues to measure
pavement quality and to set statewide short-term and long-term targets in the
MassDOT Performance Management Tracker using the Pavement Serviceability Index
(PSI), which differs from IRI. These measures and targets are used in
conjunction with federal measures to inform program sizing and project
selection.
Performance Measures |
Baseline |
2-Year Condition/ Performance |
2-year target (2020) |
4-year target (2022) |
Percentage of Pavements of the Interstate System in Good Condition |
|
75.6% |
|
70.0% |
Percentage of Pavements of the Interstate System in Poor Condition |
|
0.1% |
|
4.0% |
Percentage of Pavements of the Non-Interstate NHS in Good Condition |
32.9% |
34.1% |
30.0% |
30.0% |
Percentage of Pavements of the Non-Interstate NHS in Poor Condition |
31.4% |
31.4% |
30.0% |
30.0% |
Percentage of NHS Bridges Classified as in Good Condition |
15.1% |
15.6% |
15.0% |
16.0% |
Percentage of NHS Bridges Classified as in Poor Condition |
13.1% |
13.5% |
13.0% |
12.0% |
Reliability, Congestion, & Emissions Performance Measures (PM3)
Merrimack Valley MPO has chosen to adopt the 2-year (2020) and 4-year (2022) statewide reliability, congestion, and emissions performance measure targets set by MassDOT. MassDOT was required to adopt a statewide target by May 20th, 2018, with MPOs either adopting the statewide target or establishing their own by November 2018.
MassDOT followed FHWA regulation in measuring Level of Travel Time Reliability (LOTTR) on both the Interstate and non-Interstate NHS as well as Truck Travel Time Reliability (TTTR) on the Interstate system using the National Performance Management Research Dataset (NPMRDS) provided by FHWA. These performance measures aim to identify the predictability of travel times on the roadway network by comparing the average travel time along a given segment against longer travel times. For LOTTR, the performance of all segments of the Interstate and of the non-Interstate NHS are defined as either reliable or unreliable based on a comparison between the 50th percentile travel time and the 80th percentile travel time, and the proportion of reliable segments is reported. For TTTR, the ratio between the 50th percentile travel time and the 90th percentile travel time for trucks only along the Interstate system is reported as a statewide measure. As this data set has but one year of consistent data, FHWA guidance has been to set conservative targets and to adjust future targets once more data becomes available. To that end, MassDOTs reliability performance targets are set to remain the same. These baseline measures were revisited at the 2-year mark (2020) and reported by MassDOT in the 2020 Mid-performance report. (See table on next page.) The decision was made in the Mid-performance report to keep the LOTTR and TTTR performance targets the same.
The Merrimack Valley MPO, an agency whose planning area includes communities in the Boston Urbanized Area (UZA), and as a signatory to the 2018 Boston UZA Memorandum of Understanding (Boston UZA MOU) has also adopted 2-year (2020) and 4-year (2022) Boston UZA-wide congestion performance measure targets. These performance measures are the percentage of non-single occupancy vehicle (SOV) travel and the Peak Hour Excessive Delay (PHED). Targets were developed in coordination with state Departments of Transportation and neighboring MPOs with planning responsibility for portions of the Boston UZA.
The percentage of non-SOV travel is approximated using the U.S. Census Bureaus American Community Survey (ACS) Journey-to-Work data. In the Boston UZA, the proportion of non-SOV travel has been steadily increasing and is projected to continue increasing at a rate of 0.32% annually. The 2016 baseline measure was revisited at the 2-year mark (2020) and reported by MassDOT in the 2020 Mid-performance report. (See table on next page.) The decision was made in the Mid-performance report to develop new targets for this measure for 2020 and 2022. The new data for 2017 showed that the share of Non-Single Occupancy Vehicle Trips was 34.1%, which is higher than the 33.9% figure previously predicted by MassDOT for that year. Similarly, the 34.6% share of trips measured in 2018 was higher than the 34.2% share that was previously projected. As a result, MassDOT increased the target for 2022 to 35.8%.
PHED is measured by totaling the number of hours spent in excessive delay (defined as travel time at 20 miles per hour or at 60% of the posted speed limit, whichever is greater) in peak hours (between 6:00 am and 10:00 am, and between 3:00 pm and 7:00 pm) divided by the total UZA population. As of target-setting, there was only one year of data available. As such, the performance targets have been set flat until further data is available. This baseline measure was revisited at the 2-year mark (2020) and reported by MassDOT in the 2020 Mid-performance report. (See table on next page.) The decision was made in the Mid-performance report to keep the PHED target the same.
Emissions reduction targets are measured as the sum total of all emissions reductions anticipated through CMAQ-funded projects in non-attainment or air quality maintenance areas (currently the cities of Lowell, Springfield, Waltham, and Worcester, and the town of Oak Bluffs) identified in the Statewide Transportation Improvement Program (STIP). This anticipated emissions reduction is calculated using the existing CMAQ processes.
Measure |
Baseline |
2-Year Condition/ Performance |
2-year (2020) |
4-year (2022) |
4-year Adjusted Target |
Percent of the Person-Miles Traveled on the Interstate That Are Reliable |
70.0% |
69.1% |
68.0% |
68.0% |
|
Percent of the Person-Miles Traveled on the Non-Interstate NHS That Are Reliable |
|
82.4% |
|
80.0% |
|
Truck Travel Time Reliability (TTTR) Index |
1.84 |
1.86 |
1.85 |
1.85 |
|
Annual Hours of Peak Hour Excessive Delay Per Capita (PHED): (Urbanized Area 1) |
|
25.6 |
|
18.3 |
|
Percent of Non-Single Occupancy Vehicle (Non-SOV) Travel: (Urbanized Area 1) |
33.6% (2016) |
34.6% |
34.5% |
35.1% |
35.8% |
Total Emissions Reductions: PM2.5 |
0.000 |
|
0.000 |
0.000 |
|
Total Emissions Reductions: NOx |
0.742 |
0.490 |
0.500 |
1.600 |
1.710 |
Total Emissions Reductions: VOC |
1.667 |
0.534 |
0.600 |
0.900 |
0.559 |
Total Emissions Reductions: PM10 |
0.000 |
|
0.000 |
|
|
Total Emissions Reductions: CO |
24.452 |
6.637 |
1596.510 |
1596.510 |
6.530 |
MassDOT/ Adopted by MVMPO Performance Measures/ Targets Summary Table
Performance Measure Category |
Performance Measure |
Recent Data |
Targets |
PM1: HSIP and Safety |
Number of Fatalities Statewide (All Public Roads) |
354 average number of fatalities/ year for 2015 to 2019
|
CY 2019 Target = 353 CY 2020 Target = 347 CY 2021 Target = 339 fatalities |
PM1: HSIP and Safety |
Fatality rate per 100 million vehicle-miles traveled. |
0.56 fatalities per 100 million vehicles miles traveled per year average for 2015 to 2019 |
CY 2019 Target = 0.58 CY 2020 Target = 0.56 CY 2021 Target = 0.55 fatalities per 100 million vehicle miles traveled |
PM1: HSIP and Safety |
Number of Serious Injuries Statewide (All Public Roads) |
2,753 average number of serious injuries per year average from 2015 to 2019 |
CY 2019 Target = 2,801 CY 2020 Target = 2,689 CY 2021 Target =2,580 serious injuries |
PM1: HSIP and Safety |
Serious injury rate per 100 million vehicle-miles traveled. |
4.37 serious injuries per 100 million vehicle miles traveled per year average for 2015 to 2019 |
CY 2019 Target = 4.37 CY 2020 Target = 4.30 CY 2021 Target = 4.23 serious injuries per 100 million vehicle miles traveled |
PM1: HSIP and Safety |
Number of Non-motorized Fatalities and Non-motorized Serious Injury Statewide (All Public Roads) |
524 average number of combined serious injuries and fatalities per year for non-motorized modes for 2015 to 2019 |
CY 2019 Target = 541 CY 2020 Target = 505 CY 2021 Target = 506 combined fatalities and serious injuries for non-motorized modes |
MassDOT/ Adopted by MVMPO Performance Measures/ Targets Summary Table (Cont.)
Performance Measure Category |
Performance Measure |
Recent Data |
Targets |
PM2: Pavement and Bridge Condition |
Percentage of Pavements of the Interstate System in Good Condition Statewide |
75.6% (2-Yr Condition Mid-Performance Report) |
CY 2020 Target = 70% CY 2022 Target = 70% |
PM2: Pavement and Bridge Condition |
Percentage of Pavements of the Interstate System in Poor Condition Statewide |
0.1% (2-Yr Condition Mid-Performance Report) |
CY 2020 Target = 4% CY 2022 Target = 4% |
PM2: Pavement and Bridge Condition |
Percentage of Pavements of the non-Interstate NHS in Good Condition Statewide |
34.1% (2-Yr Condition Mid-Performance Report) |
CY 2020 Target = 30% CY 2022 Target = 30% |
PM2: Pavement and Bridge Condition |
Percentage of Pavements of the non-Interstate NHS in Poor Condition Statewide |
31.4% (2-Yr Condition Mid-Performance Report) |
CY 2020 Target = 30% CY 2022 Target = 30% |
MassDOT/ Adopted by MVMPO Performance Measures/ Targets Summary Table (Cont.)
Performance Measure Category |
Performance Measure |
Recent Data |
Targets |
PM2: Pavement and Bridge Condition |
Percentage of NHS bridges by deck area in Good Condition Statewide |
15.6% (2-Yr Condition Mid-Performance Report) |
CY 2020 Target = 15% CY 2022 Target = 16% |
PM2: Pavement and Bridge Condition |
Percentage of NHS bridges by deck area in Poor Condition Statewide |
13.5% (2-Yr Condition Mid-Performance Report) |
CY 2020 Target = 13% CY 2022 Target = 12% |
PM3: System Performance/ Freight/ CMAQ |
Percent of Person-Miles Traveled on the Interstate that are Reliable Statewide |
69.1% (2-Yr Performance Mid-Performance Report) |
CY 2020 Target = 68% CY 2022 Target = 68% |
PM3: System Performance/ Freight/ CMAQ |
Percent of Person-Miles Traveled on the Non-Interstate NHS that are Reliable Statewide |
82.4% (2-Yr Performance Mid-Performance Report) |
CY 2020 Target = 80% CY 2022 Target = 80% |
MassDOT/ Adopted by MVMPO Performance Measures/ Targets Summary Table (Cont.)
Performance Measure Category |
Performance Measure |
Recent Data |
Targets |
PM3: System Performance/ Freight/ CMAQ |
Truck Travel Time Reliability (TTTR) Index on the Interstate System Statewide |
1.86 (2-Yr Performance Mid-Performance Report) |
CY 2020 Target = 1.85 CY 2022 Target = 1.85 |
PM3: System Performance/ Freight/ CMAQ |
Annual Hours of Peak Hour Excessive Delay (PHED) per Capita in the UZA |
25.6 (2-Yr Performance Mid-Performance Report) |
2018-2019 Two-year Target = 18.3 2018-2021 Four-year Target = 18.3 |
PM3: System Performance/ Freight/ CMAQ |
Percent of Non-SOV Travel on the NHS System in the UZA |
34.6% (2-Yr Performance Mid-Performance Report) |
CY 2020 Target = 34.5% CY 2022 Target = 35.8% |
Regional Target Projects Relationship to Regional Planning Efforts and Performance Management
TIP Year |
Project Description |
Included in Regional Transportation Plan (RTP) |
Included in Regional or State Modal Plan |
Resulted from Corridor Study |
Resulted from MPO Technical Assistance Request |
Included in Other Plans (e.g. local Master Plan, CEDS, etc.) |
Projects Relationship to Performance Measures/ Other Regional Goals |
2022 |
Lawrence Intersection Improvements at Merrimack Street and South Broadway (Route 28) (# 609509) |
|
|
|
|
� One end of CEDS priority transportation project. � Is Phase 3 of Merrimack Street Corridor Improvements (other phases constructed under MassWorks Grants) � In a State Priority Development Area |
Performance Measures Project will help meet: 1) Number and Rate of Fatalities 2) Number and Rate of Serious Injuries 3) Number of non-motorized fatalities and non-motorized serious injury. 4) Percent change in Tailpipe CO2 Emissions on the NHS Compared to Calendar Year 2017 Level. 5) Percent of the Person-Miles Traveled on the non-Interstate NHS that are Reliable. Meets RTP Goals of: 1) Maintain Existing Infrastructure in State of Good Repair 2) Increase Safety for all Modes 3) Create a Multi Modal Transportation System to Support Mode Shift 4) Promote Economic Vitality 5) Transportation Equity |
Regional Target Projects Relationship to Regional Planning Efforts and Performance Management (Cont.)
TIP Year |
Project Description |
Included in Regional Transportation Plan (RTP) |
Included in Regional or State Modal Plan |
Resulted from Corridor Study |
Resulted from MPO Technical Assistance Request |
Included in Other Plans (e.g. local Master Plan, CEDS, etc.) |
Projects Relationship to Performance Measures/ Other Regional Goals |
2023 |
Lawrence Intersection Reconstruction at Marston Street & East Haverhill Street (# 610923) |
|
|
|
|
� Includes improvements in access adjacent to a CEDS Priority Project. � Lawrence Complete Streets Policy |
Performance Measures Project will help meet: 1) Number of non-motorized fatalities and non-motorized serious injury. Meets RTP Goals of: 1) Maintain Existing Infrastructure in State of Good Repair 2) Increase Safety for all Modes 3) Create a Multi Modal Transportation System to Support Mode Shift 4) Promote Economic Vitality 5)Transportation Equity |
Regional Target Projects Relationship to Regional Planning Efforts and Performance Management (Cont.)
TIP Year |
Project Description |
Included in Regional Transportation Plan (RTP) |
Included in Regional or State Modal Plan |
Resulted from Corridor Study |
Resulted from MPO Technical Assistance Request |
Included in Other Plans (e.g. local Master Plan, CEDS, etc.) |
Projects Relationship to Performance Measures/ Other Regional Goals |
2023 |
Methuen Intersection Improvements at Riverside Drive and Burnham Road (# 610658) |
|
|
|
|
� Will improve pedestrian and bicyclist access to Raymond J. Martin Riverside Park recently renovated with a Massachusetts PARC Grant. |
Performance Measures Project will help meet: 1) Number of non-motorized fatalities and non-motorized serious injury Meets RTP Goals of: 1) Maintain Existing Infrastructure in State of Good Repair 2) Increase Safety for all Modes 3) Create a Multi Modal Transportation System to Support Mode Shift 4) Transportation Equity |
Regional Target Projects Relationship to Regional Planning Efforts and Performance Management (Cont.)
TIP Year |
Project Description |
Included in Regional Transportation Plan (RTP) |
Included in Regional or State Modal Plan |
Resulted from Corridor Study |
Resulted from MPO Technical Assistance Request |
Included in Other Plans (e.g. local Master Plan, CEDS, etc.) |
Projects Relationship to Performance Measures/ Other Regional Goals |
2024 to 2026 |
North Andover Corridor Improvements on Route 114, between Route 125 (Andover Street) & Stop & Shop Driveway (# 608095) |
Yes |
|
Yes |
|
� Local Priority Development Area � North Andover Master Plan |
Performance Measures Project will help meet: 1) Number of non-motorized fatalities and non-motorized serious injury. 2) Percentage of Pavements of the non-Interstate NHS in Good condition. 3) Percent of the Person-Miles Traveled on the non-Interstate NHS that are Reliable. 4) Number and Rate of Serious Injuries Meets RTP Goals of: 1) Maintain Existing Infrastructure in State of Good Repair 2) Increase Safety for all Modes 3) Create a Multi Modal Transportation System to Support Mode Shift 4) Promote Economic Vitality 5) Promote Environmental Sustainability 6) Transportation Equity |
Regional Target Projects Relationship to Regional Planning Efforts and Performance Management (Cont.)
TIP Year |
Project Description |
Included in Regional Transportation Plan (RTP) |
Included in Regional or State Modal Plan |
Resulted from Corridor Study |
Resulted from MPO Technical Assistance Request |
Included in Other Plans (e.g. local Master Plan, CEDS, etc.) |
Projects Relationship to Performance Measures/ Other Regional Goals |
2023 to 2024 |
Salisbury Reconstruction of Route 1 (Lafayette Road) |
Yes |
|
|
|
� Will complete the roadway after a CEDS project to extend the sewer line along Route 1 is completed. � Local Priority Development Area. |
Performance Measures Project will help meet: 1) Number of non-motorized fatalities and non-motorized serious injury. 2) Percentage of Pavements of the non-Interstate NHS in Good condition. 3) Percent of the Person-Miles Traveled on the non-Interstate NHS that are Reliable. 4) Number and Rate of Serious Injuries Meets RTP Goals of: 1) Maintain Existing Infrastructure in State of Good Repair 2) Increase Safety for all Modes 3) Create a Multi Modal Transportation System to Support Mode Shift 4) Promote Economic Vitality 5) Promote Environmental Sustainability |
Performance Target(s) Project Will Help Meet
(2022 to 2026 Statewide and Regional Target Funds)
Year (s) Program-med |
City / Town |
Project Description |
Total Cost Programmed |
Federal Performance Target(s) Project Will Help Meet |
2024 to 2026 |
Andover |
Andover-Bridge Rehabilitation, A-09-036, I-495 over St 28 (SB), A-09-037, I-495 over B&M and MBTA, A-09-041, I-495 over St 28 (NB) (# 606522) |
$64,225,138 |
1) Percentage of NHS bridges classified as in Good condition. 2) Percentage of Pavements of the Interstate System in Good Condition and in Poor Condition 3) Percent of the Person-Miles Traveled on the Interstate that are Reliable. 4) Truck Travel Time Reliability (TTTR) Index on the Interstate System.
|
2025 |
George- town/ Boxford |
Georgetown-Boxford Border to Boston Trail, from Georgetown Road to West Main Street (Route 97) (# 607541) |
$2,714,316 |
1) Number of non-motorized fatalities and non-motorized serious injury. 2) Percent change in Tailpipe CO2 Emissions on the NHS Compared to Calendar Year 2017 Level. |
2025 |
George-town/ Newbury |
Georgetown-Newbury Border to Boston Trail, (Northern Georgetown to Byfield Section) (# 607542) |
$5,685,060 |
Number of non-motorized fatalities and non-motorized serious injury. |
Performance Target(s) Project Will Help Meet
(2022 to 2026 Statewide and Regional Target Funds)
Year (s) Program-med |
City / Town |
Project Description |
Total Cost Programmed |
Federal Performance Target(s) Project Will Help Meet |
2022 |
Haverhill |
Haverhill Bridge Replacement, H-12-039, I-495 (NB & SB) over Merrimack River (# 605306) (AC Yr 5 of 5) |
$12,994,233 |
1) Percentage of NHS bridges classified as in Good condition. 2) Percentage of Pavements of the Interstate System in Good Condition and in Poor Condition 3) Percent of the Person-Miles Traveled on the Interstate that are Reliable. 4) Truck Travel Time Reliability (TTTR) Index on the Interstate System.
|
2024 to 2026 |
Haverhill |
Haverhill Bridge Replacement, H-12-040, I-495 (NB & SB) over Merrimack River (#609466) (AC Yrs 4 of 4) |
$78,161,628 |
1) Percentage of NHS bridges classified as in Good condition. 2) Percentage of Pavements of the Interstate System in Good Condition and in Poor Condition 3) Percent of the Person-Miles Traveled on the Interstate that are Reliable. 4) Truck Travel Time Reliability (TTTR) Index on the Interstate System.
|
Performance Target(s) Project Will Help Meet
(2022 to 2026 Statewide and Regional Target Funds) (Cont.)
Year (s) Program-med |
City / Town |
Project Description |
Total Cost Programmed |
Federal Performance Target(s) Project Will Help Meet |
2024 to 2026 |
Haverhill |
Haverhill Bridge Replacement, H-12-007 & H-12-025, Bridge Street (SR 125) over the Merrimack River (# 605304) (AC Yrs 1,2 & 3 of 5) |
$57,381,766 |
1) Percentage of NHS bridges classified as in Good condition. 2) Percentage of Pavements of the Non-Interstate NHS in Good Condition and in Poor Condition 3) Percent of the Person-Miles Traveled on the Non-Interstate NHS that are Reliable.
|
2022 |
Lawrence |
Lawrence Intersection Improvements at Merrimack Street and South Broadway (Route 28) (# 609509) |
$1,502,354 |
1) Number and Rate of Fatalities 2) Number and Rate of Serious Injuries 3) Number of non-motorized fatalities and non-motorized serious injury. 4) Percent change in Tailpipe CO2 Emissions on the NHS Compared to Calendar Year 2017 Level. 5) Percent of the Person-Miles Traveled on the non-Interstate NHS that are Reliable. |
2022 |
Lawrence |
Lawrence Intersection Reconstruction at Marston Street & East Haverhill Street (# 610923) |
$1,658,011 |
Number of non-motorized fatalities and non-motorized serious injury.
|
Performance Target(s) Project Will Help Meet
(2022 to 2026 Statewide and Regional Target Funds) (Cont.)
Year (s) Program-med |
City / Town |
Project Description |
Total Cost Programmed |
Federal Performance Target(s) Project Will Help Meet |
2025 |
Lawrence |
Lawrence Community Day Arlington Improvements (SRTS) (# 612002) |
$1,611,774 |
Number of non-motorized fatalities and non-motorized serious injury.
|
2026 |
Lawrence |
Lawrence Bridge Replacement, L-04-012, Short Street over Spicket River (# 612074) |
$3,402,326 |
|
2023 to 2024 |
Lawrence |
Lawrence Lawrence-Manchester Rail Corridor (LMRC) Rail Trail (# 608930) |
$21,416,304 |
Number of non-motorized fatalities and non-motorized serious injury |
2023 |
Methuen |
Methuen Intersection Improvements at Riverside Drive and Burnham Road (# 610658) |
$1,500,000 |
Number of non-motorized fatalities and non-motorized serious injury |
2022 |
Newbury-Newburyport-Salisbury |
Newbury-Newburyport-Salisbury-Resurfacing and related work on Route 1 (# 608494) |
$9,722,950 |
Percentage of Pavements of the non-Interstate NHS in Good condition.
|
Performance Target(s) Project Will Help Meet
(2022 to 2026 Statewide and Regional Target Funds) (Cont.)
Year (s) Program-med |
City / Town |
Project Description |
Total Cost Programmed |
Federal Performance Target(s) Project Will Help Meet |
2024 to 2026 |
North Andover |
North Andover-Corridor Improvements on Route 114, between Route 125 (Andover Street) & Stop & Shop Driveway (# 608095) |
$24,860,071 |
1) Number of non-motorized fatalities and non-motorized serious injury. 2) Percentage of Pavements of the non-Interstate NHS in Good condition. 3) Percent of the Person-Miles Traveled on the non-Interstate NHS that are Reliable. 4) Number and Rate of Serious Injuries
|
2023 |
Rowley |
Rowley Safety Improvements at Route 1, Central and Glen Streets (# 609392) |
$1,486,378 |
1) Number and rate of fatalities. 2) Number and rate of Serious Injuries
|
2023-2024 |
Salisbury |
Salisbury Reconstruction of Route 1 (Lafayette Road) (# 602202) |
$18,214,824 |
Number of non-motorized fatalities and non-motorized serious injury. |
Transit Asset Management (TAM) Plan Performance Management Targets
The MVRTA completed its TAM Plan March 6, 2020. The Performance Management Targets were adopted by the MVRTA Advisory Board on May 7, 2020. The Merrimack Valley MPO adopted these targets at its May 27, 2020 MPO meeting.
The following information is from the MVRTA Transit Asset Management Plan prepared 3/6/2020.
Annual Performance Targets and Measures
As a recipient of Federal Transit Administration funds, the MVRTA is required to develop and maintain a Transit Asset Management Plan per FTAs Final Rule at 49 CFR Part 625. As defined by the Rule, Transit Asset Management (TAM) is the strategic and systematic practice of processing, operating, inspecting, maintaining, rehabilitating and replacing transit capital assets to manage their performance, risks and cost over their life cycles to provide safe, cost effective and reliable public transportation.
The preparation of the TAM is based on identifying the transit assets which the MVRTA owns and has direct Capital responsibility for and the performance measures included in the Final Rule that relate to these identified assets.
|
Performance Measure |
Equipment Non-revenue support-service and maintenance vehicles |
Percentage of vehicles met or exceeded Useful Life Benchmark |
Rolling Stock Revenue vehicles by mode, bus/ van |
Percent of vehicles met or exceeded Useful Life Benchmark |
Facilities Maintenance and administrative facilities: and passenger stations (buildings) and parking facilities |
Percentage of Assets with condition rating below 3.0 on FTA TERM Scale. |
Using these Performance Measures leads to the setting of targets against the defined Useful Life Benchmark (ULB). Which FTA defines as:
The expected lifecycle of a capital asset for a particular Transit Providers operating environment, or the acceptable period of use in service for a particular Transit Providers operating environment. |
The MVRTA has defined the ULB as presented in FTA circular C 5010.1E for buses and vans:
Minimum Service-life for Buses and Vans
|
|
Minimum Life |
|
|
|
(Whichever comes first) |
|
Category |
Length |
Years |
Miles |
Heavy-Duty Large Bus |
35 to 45 ft. |
12 |
500,000 |
Heavy-Duty Small Bus |
30 ft. |
10 |
350,000 |
Medium-Duty Transit Bus |
30 ft. |
7 |
200,000 |
Light-Duty Mid-Sized Bus |
25 to 35 ft. |
5 |
150,000 |
Light Duty Small Bus, Cutaways and Modified Van |
16 to 28 ft. |
4 |
100,000 |
For TAM Plan dated 3/6/2020, the MVRTA has prepared the following targets:
Transit TAM Targets
Percent of revenue vehicles that have met or exceeded their useful life benchmark:
|
FFY 2020 |
FFY 2021 |
FFY 2022 |
FFY 2023 |
Bus |
0% |
18% |
8% |
8% |
Van |
0% |
70% |
0% |
26% |
Non-revenue vehicles-percent of service vehicles that have met or exceeded their useful life benchmark:
|
FFY 2020 |
FFY 2021 |
FFY 2022 |
FFY 2023 |
Maintenance Trucks |
0% |
0% |
0% |
0% |
SUV (Supervisory Vehicles) |
12% |
12% |
25% |
12% |
Facility-percent of facilities rated below 3 on the FTA condition scale:
Passenger/ Parking facilities 0% (McGovern Center, Gateway Surface Parking, Haverhill Intermodal Parking, Costello Center)
Administrative/ maintenance facilities 0% (85 Railroad Ave. HQ)
Updates to these targets will be done in conjunction with the preparation of the next TAM Plan and the FY 2022 to 2026 Capital Plan.
In May of 2020 the Merrimack Valley MPO voted to adopt the transit TAM performance measure targets set by MVRTA for FFY 2020 through FFY 2023.
The following table lists the transit projects programmed in this TIP that help meet the Transit TAM Performance Measures.
TAM Performance Measures Transit Projects Help Meet
Year |
Project Title |
Performance Measure Project helps meet |
2022 |
MVRTA Replace 9 Model Year 2009 35 ft. Buses Delivery 2022 (RTD0009673) |
Rolling Stock-Percent of vehicles met or exceeded Useful Life Benchmark |
2022 |
MVRTA Replace 1 Model Yr 2016 Supervisory Vehicle (RTD0009680) |
Equipment-Percent of vehicles met or exceeded Useful Life Benchmark |
TAM Performance Measures Transit Projects Help Meet (Cont.)
Year |
Project Title |
Performance Measure Project helps meet |
2022 |
MVRTA HQ Facility Repairs (RTD0010053) |
Facilities-Percentage of Assets with condition rating below 3.0 on FTA TERM Scale. |
2023 |
MVRTA Replace 8 Model Yr 2011 35 ft. buses delivery 2023 (RTD0009677) |
Rolling Stock-Percent of vehicles met or exceeded Useful Life Benchmark |
2023 |
MVRTA Replace 6 Model Yr 2017 Type E-2 vans delivery 2023 (RTD0009678) |
Rolling Stock-Percent of vehicles met or exceeded Useful Life Benchmark |
2023 |
MVRTA Replace 1 Model Yr 2017 supervisory vehicle (RTD0009687) |
Equipment-Percent of vehicles met or exceeded Useful Life Benchmark |
2024 |
MVRTA Replace 1 Model Year 2018 Supervisory Vehicle (RTD0009688) |
Equipment-Percent of vehicles met or exceeded Useful Life Benchmark |
2024 |
MVRTA Replace 8 model yr 2012 35 ft. buses delivery 2024 (8 of 8) (RTD0009681) |
Rolling Stock-Percent of vehicles met or exceeded Useful Life Benchmark |
2025 |
MVRTA Replace 1 Model Year 2019 Supervisory Vehicle (RTD00009693) |
Equipment-Percent of vehicles met or exceeded Useful Life Benchmark |
2026 |
MVRTA Replace 1 Model Year 2020 Supervisory Vehicle (RTD00010060) |
Equipment-Percent of vehicles met or exceeded Useful Life Benchmark |
Public Transportation Agency Safety Plan (PTASP)
The MVRTA, as a recipient of FTA Urban Area Funding Grants, is required to develop a plan to implement a Safety Management System (SMS) that includes safety performance targets. The MVRTA approved the Merrimack Valley Regional Transit Authority Safety Plan on November 10, 2020 and Revised 1/15/2021.
Transit Safety Performance Targets
The following is from the MVRTA Safety Plan:
Safety Performance Targets have been set for each of the 3 modes of transit service. They are based on the safety performance measures established by MVRTA over the last 3 Fiscal Years. All goals are expressed in number of occurrences per 100,000 miles. Below are the goals set by the MVRTA for our service.
Mode |
Fatalities |
Fatalities (per 100 thousand VRM) |
Injuries (Total) |
Injuries (per 100 thousand VRM) |
Safety Events |
Safety Events (per 100 thousand VRM) |
System Reliability (VRM/ Failures) |
Motor Bus |
0 |
0 |
0 |
0 |
0 |
0 |
46461 |
Commuter Bus |
0 |
0 |
0 |
0 |
0 |
0 |
For all |
Demand Response |
0 |
0 |
0 |
0 |
0 |
0 |
3 modes |
The FFYs 2022 to 2026 Merrimack Valley Metropolitan Planning Organizations Transportation Improvement Program (TIP) contains Federal-aid project programming information for five years. For each year, gross estimates of project costs are listed in the federal fiscal year (FFY) of the proposed advertise date. Federal fiscal years begin on October 1 and run through September 30. For example, FFY 2022 begins on October 1, 2021 and ends on September 30, 2022. The advertising dates shown for roadway projects were determined based on information provided by the Capital Expenditure and Program Office within MassDOT, the MassDOT District 4 Office, and MVMPO member communities. The MVRTA and MassDOTs Rail and Transit Division determined programming dates for transit projects.
Projects are programmed in the regions TIP based on a number of factors. These include the projects score based upon the MPOs Transportation Evaluation Criteria (TEC), project cost and the availability of STBG funding in the years covered in the document. Most of the time the community is responsible for funding the design of a project and therefore their priorities greatly influence which projects will be far enough along in the design process to be programmed in the TIP. The MPO process solicits community project priorities when developing the RTP and, when annually developing the UPWP, the communities are asked what transportation studies they would like the MPO to conduct for them. These often but not always are related to the project priorities that were identified in the RTP. These studies become the beginning of many locally-generated project proposals.
Road and bridge project selection is also largely dependent upon the current and expected design status for each project, which can be affected by such factors as environmental permitting and Right-of-Way (ROW) status. When it comes to programming projects in the TIP, readiness becomes paramount, because the project needs to be through the 100% design process to be able to be advertised for construction.
For bridge projects, information from MassDOTs Bridge section is given primary consideration when scheduling projects.
Transportation Evaluation Criteria
In 2003, the MPOs worked with the then Massachusetts Executive Office of Transportation and Public Works (EOTPW) to develop objective evaluation criteria that could be applied to transportation projects in the Commonwealth. Early in 2004, EOTPW asked planning staff from the then MassHighway Planning, the MassHighway district offices and the regional planning agencies to apply these criteria to projects within their respective Metropolitan Planning Organizations (MPOs). Application of these criteria include not only an evaluation of the magnitude of improvement in the condition, mobility, and safety of transportation projects, but also an evaluation of their community effects and support, the land use and economic development impact, and the environmental effects. A score valued from-3 to 3 is assigned to each of the criteria. In fact, there is at least one score associated with each of the FAST Act ten planning factors. The scores within each category are averaged and then the category averages are added together to reach the total score. The following chart illustrates the data and scoring criteria for each TEC element as well as the planning factors considered in each element, and which TEC elements relate to the performance measures.
Consideration of whether a project contributes to Climate Resiliency was added to the TEC process for the MVMPO 2021 to 2025 TIP in the Environmental Effects section of the evaluation form, under the Air Quality/Climate Effects scoring component. The project receives one point under this criteria if the project involves widening a culvert and the project receives one point if it raises a facility (for example a bridge, roadway or trail) in a flood prone area.
The COVID-19 pandemic has not impacted the project scoring for this TIP. While the changes to travel patterns caused by the pandemic are certainly dramatic, it was not deemed necessary to change project scores or the transportation evaluation criteria at this time. The changes to travel patterns that have been observed in the Merrimack Valley and elsewhere in Massachusetts and New England, both under total lock down and phased re-openings of the economy, are not likely going to continue in the longer term. Consequently, it was considered inadvisable to change project scores or plans based on a temporary condition. The MVMPO will continue to monitor traffic counts and travel time reliability, but it will likely take at least a year and probably longer for travel patterns to settle into the new normal, whatever that is going to be.
The RITIS platform is a primary data source used to inform the Merrimack Valley MPOs Congestion Management Process (CMP). The data generated by the CMP on travel times and travel reliability on the regions NHS roadways is then considered in the roadway and trail project scoring system to evaluate the degree to which the magnitude and duration of congestion on the transportation network will be reduced through the construction of the proposed improvements.
The MVMPOs CMP currently considers RITIS travel time reliability and travel time data collected through the year 2019. As the RITIS data is slightly different than previously available travel time data, there are only a few years of this newer data to compare and it shows that there had not been much change in travel time reliability, or change in travel patterns. However, now that travel patterns have changed dramatically due to the COVID-19 pandemic and are likely to continue changing as travel reaches its new normal in a few years, we will then be able to examine how congestion and travel patterns have changed using the RITIS platform.
The following table provides the TEC scoring guidelines for each element scored, as well as, the Planning Factors and Performance Measures related to each scoring element.
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
Condition |
|
|
|
|
A. Magnitude of pavement condition improvements |
Use Pavement Condition Index (PCI) (if available) to rate current condition as excellent, good, fair, or poor. If not available, use pavement condition description from other sources. |
Poor = 3 to 2 Fair = 2 to 1 Good = 1 to 2 Excellent = 0 to 1
|
Pavement conditions often vary across the project limits, and therefore scores have a range. Excellent current condition may score a 1 if project is not expected to be programmed for several years. |
Preservation; Safety; Resiliency & reliability; Economic Vitality. Contributes to meeting Pavement Performance Measure Targets of 70% Interstate or 30% Non-Interstate NHS Pavements in Good Condition and/or 4% max. Interstate or 30% max. Non-Interstate Pavements in Poor Condition Statewide |
B. Magnitude of improvement of other infrastructure |
Types and number of upgrades |
Major Upgrade such as widening a bridge = 3 Multiple upgrades from list of drainage improvements, new sidewalks, new signals, signal upgrades, adding turn lanes, etc. = 3 to 2 One or two of above upgrades = 2 to 1 No Upgrades = 0 |
|
Preservation; Safety; Resiliency & reliability; Accessibility & mobility; Environmental and economic sustainability; Enhance travel & tourism; Note that all roadway projects consider drainage improvements. |
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
|
||||
Mobility |
|
|
|
|
|
||||
A. Effect on magnitude and duration of congestion |
Magnitude of current congestion, measured by Level of Service, traffic delays, or queue lengths, if available. If there is not currently congestion, then score is zero unless project causes congestion. |
Significant reduction in congestion = 3 Moderate reduction in congestion = 2 Small reduction in congestion = 1 No change in congestion = 0 Small increase in congestion = -1 Moderate increase in congestion = -2 Significant increase in congestion = -3 |
If there is not currently congestion, then score is zero unless project causes new congestion. |
Economic Vitality; Accessibility and Mobility; Resiliency and reliability; Enhance travel and tourism. Contributes to meeting System Performance Measure Targets of 68% Interstate or 80% Non-Interstate NHS person-miles travelled that are reliable Statewide and/or 1.85 Truck Travel Time Reliability Index Statewide |
|
||||
B. Effect on travel time and connectivity / access |
Types and numbers of upgrades, such as, improves travel time by widening shoulders, or signal improvements; provides new access, connects existing trails, etc. |
Major Upgrade such as providing new roadway access = 3 Multiple upgrades from signal improvements, new sidewalks, adding turn lanes, new trail = 3 to 2 One or two of above upgrades, or new = 2 to 1 No Upgrades = 0 |
Additional point (not above 3) if providing connectivity between schools, businesses, and other activity centers. |
Economic Vitality; Accessibility and Mobility; Resiliency and reliability; Connectivity; Enhance travel and tourism. |
|
||||
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
|||||
Mobility |
|
|
|
|
|||||
C. Effect on other modes using the facility |
Types and numbers of upgrades to Other modes (means of travel) |
Major Upgrade for Other mode of transportation = 3 Multiple upgrades from adding bike lanes, new sidewalks, wheelchair ramps, proximity to transit facilities = 3 to 2 One or two of above upgrades = 2 to 1 No Upgrades to Other modes = 0 |
|
Economic Vitality; Safety; Security; Accessibility and Mobility; Environmental and economic sustainability; Connectivity; Resiliency and reliability; Enhance travel and tourism. Contributes to meeting System Performance Measure Target of 34.5% Non-SOV travel on the NHS in the UZA |
|||||
D. Effect on regional and local traffic |
Whether affects traffic outside of the project limits locally, and beyond that, regionally |
Is on the NHS, a State numbered route, connector, or highly traveled local road; and: Substantially improves traffic regionally = 3 Moderately improves traffic regionally = 2 to 1 Substantially or moderately improves traffic locally = 2 to 1 Neutral = 0 Negative scores if adversely affects traffic to the degrees and geography above. |
|
Economic Vitality; Accessibility and Mobility; Efficient System Management; Enhance travel and tourism. |
|||||
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
||||
Safety and Security |
|
|
|
|||||
A. Effect on crash rate compared to State average |
Whether location is designated a State defined Crash Cluster location (HSIP eligible) and the EPDO score assigned by that performance measure, or crash rate compared to State average, other safety concerns |
High EPDO score, crash cluster, Top 100 crash locations = 3 Higher than average crash rate/ EPDO score = 2 Lower than average crash rate, but safety concerns are being addressed = 1 No effect on crash rate = 0 |
Safety; Efficient System Management; Resiliency and Reliability. Contributes to meeting HSIP and Safety Performance Measure Targets for number of fatalities and serious injuries, rates of fatality and serious injury Statewide on all public roads. |
|||||
B. Effect on bicycle and pedestrian safety |
Includes improvements that effect bicycle and pedestrian safety or is detrimental to pedestrian bicycle safety. |
Major Upgrade, separate bike lane, or shared use path = 3 Multiple upgrades from list of widening shoulders for bikes; new or improved sidewalks; new pedestrian signals; wheelchair ramps; etc. = 3 to 2 One or two of above upgrades = 2 to 1 No Upgrades = 0 Could use negative scores if detrimental to bike / pedestrian safety |
Additional point (not above 3) if improvements are near schools or other areas frequented by bicyclists and/ or pedestrians, or there is a history of crashes involving bikes and/or pedestrians. |
Safety; Resiliency and Reliability; Enhance Travel and Tourism. Contributes to meeting HSIP and Safety Performance Measure Targets for Number of non-motorized fatalities and serious injuries Statewide on all public roads. |
||||
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
||||
Safety and Security (Cont.) |
|
|
|
|||||
C. Effect on transportation security and evacuation |
Is on the NHS. Is a community designated evacuation route. Is within 10 miles of a nuclear power plant. |
Will significantly improve travel along an evacuation route = 3 Is an evacuation route within 10 miles of a nuclear power plant, or is on the NHS and improves travel = 2 Is an evacuation route or Is within 10 miles of a nuclear power plant, or in on the NHS = 1 Is not any of the 3 listed in the data column = 0 |
|
Security; Safety. |
||||
Community Effects and Support |
|
|
||||||
A. Residential effects: ROW, noise, aesthetic, cut through traffic, and other. |
Degree of effect on residential aspects. |
Improves these aspects: Significantly = 3 Moderately = 2 Slightly = 1 No effect on these aspects = 0 Creates negative effects from these aspects: Slightly = -1 Moderately = -2 Significantly = -3 |
|
Environmental Sustainability; |
||||
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
Community Effects and Support (Cont.) |
|
|
||
B. Public, local government, legislative, and regional support |
Degree of support. |
Improves these aspects: Greatly Supported = 3 Moderately Supported = 2 Somewhat Supported = 1 Not Supported, or unknown = 0 Some Opposition = -1 |
|
|
C. Effect on service to minority or low-income neighborhoods. (Title VI and EJ) |
Increased or decreased service to Title VI and EJ neighborhoods |
Improves service to Title VI or EJ neighborhoods: Significantly = 3 Moderately = 2 Slightly = 1 No effect on Title VI or EJ neighborhood = 0 Slightly decreased service = -1 Moderately decreased service = -2 Significantly decreased service = -3
|
|
Quality of Life; Accessibility and Mobility; Resiliency and Reliability; Enhance Travel and Tourism. |
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
Community Effects and Support (Cont.) |
|
|
||
D. Other impacts / benefits to minority or low-income neighborhoods. (Title VI and EJ) |
Number / degree of positive or negative impacts to Title VI and EJ neighborhoods |
Positive Impacts to Title VI or EJ neighborhoods: Significant = 3 Moderate = 2 Slight = 1 No effect on Title VI or EJ neighborhood = 0 Negative Impacts to Title VI or EJ neighborhoods: Slight = -1 Moderate = -2 Significant = -3 |
|
Quality of Life. |
E. Effect on development and redevelopment of housing stock |
Number / degree of positive or negative effects on development and redevelopment of housing stock |
Positive Impacts to development / redevelopment of housing stock: Significant = 3 Moderate = 2 Slight = 1 No effect on development or redevelopment of housing stock = 0 Negative Impacts to development/ redevelopment of housing stock: Slight = -1 Moderate = -2 Significant = -3
|
|
Economic Vitality; Quality of Life. |
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
Land Use and Economic Development |
|
|
||
A. Business effects: ROW, noise, traffic, parking, freight access and other. |
Degree of effect on business aspects. |
Improves these aspects: Significantly = 3 Moderately = 2 Slightly = 1 No effect on these aspects = 0 Creates negative effects from these aspects: Slightly = -1 Moderately = -2 Significantly = -3
|
|
Economic Vitality; Accessibility and Mobility. |
B. Sustainable development effects. Consistent with Merrimack Valley Priority Growth Strategy (MVPGS). |
Number/ degree of positive or negative effects on sustainable development and proximity to State and/or Regional Priority Development Areas (PDA) |
Positive Impacts to sustainable development: Significant = 3 Moderate = 2 Slight = 1 No effect on development or redevelopment of housing stock = 0 Negative Impacts to development/ redevelopment of housing stock: Slight = -1 Moderate = -2 Significant = -3
|
Additional points, (not above 3) if located in or near a State or Regional Priority Development Area |
Economic Vitality; Consistency with State and local planned growth. |
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
Land Use and Economic Development (Cont.) |
|
|
||
C. Consistent with regional land-use and economic development plans and Merrimack Valley Priority Growth Strategy (MVPGS). |
Degree of consistency with regional plans |
Consistent with regional plans: Significantly = 3 Moderately = 2 Slightly = 1 Neutral = 0 Not Consistent with regional Plans: Slightly = -1 Moderately = -2 Significantly = -3
|
Additional points (not above 3) if located in or near a Regional Priority Development Area |
Economic Vitality; Consistency with State and local planned growth and economic development plans. |
D. Effect on job creation. |
Estimated job creation |
Effect on job creation: Significant = 3 Moderate = 2 Slight = 1 Neutral = 0 Elimination of jobs: Slight = -1 Moderate = -2 Significant = -3
|
|
Economic Vitality. |
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
Environmental Effects |
|
|
||
A. Air Quality / Climate effects |
Green House Gas Analysis Results |
Effect on Air Quality: Quantified decrease in emissions = 2 or 1 Qualitative decrease in emissions = 1 No effect on emissions = 0 Qualitative increase in emissions = -1 Quantified increase in emissions = -2 or -1 Climate Effects Resiliency: A culvert is being widened = 1 A facility (ex. bridge, road or trail) in a flood prone area is being raised = 1 |
|
Protect and Enhance the Environment. Preservation; Resiliency & reliability; Reduce or mitigate stormwater impacts; Contributes to meeting CMAQ Performance Measure Target of 18.3 Annual Hours of Peak Hour Excessive Delay (PHED) per Capita in the UZA |
B. Water Quality/ supply effects; wetlands effects. |
Number/ degree of positive or negative effects on water quality / supply effects; wetlands effects. |
Effect on Water Quality / supply and wetlands: Positive effect: Significant = 3 Moderate = 2 Slight = 1 Neutral = 0 Negative Effect: Slight = -1 Moderate = -2 Significant = -3 |
|
Protect and Enhance the Environment; Reduce or mitigate stormwater impacts. |
TEC Element |
Data |
Scoring |
Additional Notes |
Planning Factors/ Performance Measures |
Environmental Effects (Cont.) |
|
|
||
C. Historic and cultural resource effects |
Proximity / degree of positive or negative effects on historic and cultural resources |
Positive effect on historic and cultural resources: Significant = 3 Moderate = 2 Slight = 1 Neutral = 0 Negative Effect: Slight = -1 Moderate = -2 Significant = -3 |
Often considers improved access to nearby resources. |
Economic Vitality; Accessibility and Mobility; Quality of Life; Enhance Travel and Tourism. |
D. Effect on wildlife habitat and endangered species. |
Location of project in State Estimated Habitat of Rare Wildlife or State Priority Habitat of Rare Species |
Positive effect on wildlife or endangered species in a State designated area: Significant = 3 Moderate = 2 Slight = 1 Not in a wildlife or endangered species area = 0 Negative effect on wildlife or endanger species in a State designated area.: Slight = -1 Moderate = -2 Significant = -3 |
� |
Protect and Enhance the Environment. |
The resulting Transportation Evaluation Criteria (TEC) scores for selected projects in the Merrimack Valley region that were derived by applying these criteria are shown in Appendix C. It is the goal of the MVMPO that these criteria ratings, along with information related to the readiness of projects, will make the planning process, and more specifically, the selection and prioritization of projects, more transparent to the general public. A sample project evaluation sheet showing the various criteria is in Appendix D.
The use of these TEC scores also allows the Merrimack Valley MPO to meet FAST Act requirements for programming Transportation Alternatives (TA) funding (similar to TAP funding from the previous legislation). TA funding is a set-aside of Surface Transportation Block Grant Programming (STBG) through a competitive process and, in general, helps to manage performance by focusing available funding on the highest regional priorities. It also helps to draw attention to the reader that FAST Act is a very Performance Measure -oriented piece of legislation.
The principal objective of this document is the provision of an additional point for public access to and review of the transportation planning process. This FFYs 2022 to 2026 Transportation Improvement Program was developed in accordance with the Public Participation Process established for the Merrimack Valley Metropolitan Planning Organization (MVMPO). The MVMPO amended its current Public Involvement Process in March of 2017, it is contained in the MVMPO Public Participation Plan as Amended through March 2017 on the MVPC website under Transportation Reports. The Process applies to the development of the Transportation Improvement Program (TIP), the Regional Transportation Plan (RTP) and the Unified Planning Work Program (UPWP). The Public Involvement Process endorsed by the MVMPO is also used by the MVRTA as its public involvement process. The notice of public involvement and time established for review and comment for the development of this TIP satisfies the Program of Project requirements established by the Federal Transit Administration (FTA).
The Merrimack Valley MPOs Public Participation Plan as amended through March 2017, reflects the consultation requirements identified in the FAST Act of 2015 and prior federal transportation authorizations, and the existing transportation planning regulations developed by the U.S. Department of Transportation for the development of Regional Transportation Plans and Transportation Improvement Programs. This document identifies a number of stakeholders to be consulted in developing these documents. In developing the Draft FFYs 2022 to 2026 Transportation Improvement Program, all MVMPO stakeholders were given notice that the process of developing the FFYs 2022 to 2026 TIP was beginning. Stakeholders were also notified of the availability of the draft document for public review and comment.
Listed below are categories of interested individuals, organizations and other stakeholders (Interested Parties) identified by the MVMPO for inclusion in the PPP. They are defined based on the individual groups identified in the FAST Act of 2015 and prior federal transportation authorizations, and the existing transportation planning regulations developed by the U.S. Department of Transportation.
The MVMPO continues to add individuals, organizations or other stakeholders to this list and their addition is not considered an act requiring the formal amendment of the PPP. Similarly, any of the individuals or organizations identified below may request to be removed from the mailing list and such action does not necessitate a formal PPP amendment.
Individuals, including:
Interested individuals, business persons
Merrimack Valley Transportation Committee (MVTC) members
City/Town Clerks
MVMPO Region Congressional Delegation
MVMPO Region Legislative Delegation
Affected public agencies, including:
Boards of Selectmen / City Councils
Chief Elected Officials
City and Town Engineers
Federal Emergency Management Agency
Federal Highway Administration
Federal Transit Administration
Greater Derry-Salem Cooperative Alliance for Regional Transportation (CART)
Local Departments of Public Works
Local Police Departments
Local Traffic and Safety Committees
Massachusetts Department of Environmental Protection
MBTA Commuter Rail Officials
Affected public agencies, including (Cont.):
Massachusetts Executive Office of Housing and Economic Development
Massachusetts Executive Office of Public Safety and Security
MassDOT
Merrimack Valley Regional Transit Authority
Metropolitan Area Planning Council
Nashua Regional Planning Commission
Rockingham Planning Commission
U.S. Environmental Protection Agency
Representatives of public transportation employees, including:
Truck Drivers Union Local #170
Freight shippers, including:
P.J. Murphy Transportation
JB Hunt
Estes Express
Shaheen Brothers
ABF Freight
PanAm Railways
Bonneys Express
Providers of freight transportation services, including:
United Parcel Service
Federal Express
Private profit-and non-profit providers of transportation in the
region, including:
Assist Incorporated
C&J Transportation
Cape Ann Transit Authority (CATA)
Central Wheelchair and Van Transportation
EMT Corporation
Local Taxi Companies
Northern Essex Elder Transportation (NEET)
Other Transportation Providers Identified in the Regional Transportation Plan
The Coach Company
TransCare
Representatives of users of public transportation, including:
American Training, Inc.
Cambridge College
Community Action Incorporated (CAI)
Emmaus, Inc.
Elder Services of the Merrimack Valley
Local Senior Centers/Councils on Aging
Northeast Independent Living Program
Merrimack College
Merrimack Valley Hospice
Merrimack Valley Workforce Investment Board, Inc.
Northern Essex Community College
Office of Employment Services
Representatives of bicyclist and pedestrian advocacy organizations,
including:
Andover Trails Committee
Bay Circuit Alliance
Coastal Trails Coalition
Essex National Heritage Commission
Essex County Trail Association
Groveland Open Space and Recreation Committee
Representatives of bicyclist and pedestrian advocacy organizations,
Including (Cont.):
MassBike
Merrimack Valley Off-Road Trails Committee
Representatives for the community of individuals with disabilities,
including:
Executive Office of Health and Human Services
Northeast Independent Living Program
Department of Mental Health
Massachusetts Commission for the Blind
Area Nursing Homes
United Cerebral Palsy
CLASS Inc.
Fidelity House
Association of Retarded Persons (ARC)
Organizations and facilities that serve low-income and minority households who traditionally have been underserved by existing transportation systems and may face challenges accessing employment and other services, including:
MVRTA Transit Centers in Amesbury, Haverhill and Lawrence (post notices)
Social Security Offices
Employment Offices (post notices)
Ethnic, Civic/Social, Faith-Based and Veterans Organizations
Merrimack Valley Goodwill
Area Hospitals
Salvation Army
Groundwork Lawrence
Lawrence Community Works
United Way of the Merrimack Valley
Methuen Arlington Neighborhood, Inc.
YMCA/YWCA
Agencies and officials responsible for other planning activities within the MPA that are affected by transportation, including:
State and local planned growth:
Area Planning Boards
Mass Development
Merrimack Valley Transportation Management Association
The Junction Transportation Management Organization
Economic development:
Chambers of Commerce
Economic Development Administration
Local Community Development Directors
Merrimack Valley Economic Development Council
Environmental agencies and federal lands:
Andover Village Improvement Society (AVIS)
Essex County Greenbelt Association
Local Conservation Commissions
MassRiverways
Merrimack River Watershed Council
National Park Service
Powwow River Watershed Association
Parker River Clean Water Association
Shawsheen River Watershed Association
Trustees of Reservations
U.S. Environmental Protection Agency (EPA)
U.S. Fish and Wildlife Service
d. Airport operations:
Lawrence Airport Commission
e. Other Interested Parties
Conservation Law Foundation
The notices were sent directly to almost 650 email addressees representing these groups. Notices were put in newspapers and on cable community television directing the public to the MVPC website which contained the notice and the materials for review.
In addition to these direct mailings, and in accordance with this process, public notice of the Draft FFYs 2022 to 2026 Transportation Improvement Program was published in the Lawrence Eagle Tribune, Newburyport Daily News, Haverhill Gazette (Published Weekly) and Rumbo News informing the public of its right to comment on the document which would be available on the MVPC website from May 5, 2021 through May 25, 2021. It said that comments would be received through May 25, 2021 and that two separate Virtual public hearings on the document would take place on May 19, 2021 from 1:00 p.m. to 2:00 p.m. and from 6:00 p.m. to 7:00 p.m. The meetings were held Virtually due to COVID-19 Virus restrictions. The MVMPO will summarize comments that are received during the 21-day review and comment period and will include this summary in the Final FFYs 2022 to 2026 TIP.
Public input in developing the TIP was sought at the following meetings in 2020 and 2021:
� December 30, 2020, January 27, 2021, February 24, 2021, March 24, 2021, April 28, 2021 and May 26, 2021 MVMPO Meetings (all held Virtually due to COVID-19 Virus restrictions)
� February 4, 2021, March 4, 2021, April 1, 2021 and May 6, 2021 MVRTA Advisory Board meetings (all held Virtually due to COVID-19 restrictions)
� March 18, 2021, April 15, 2021,and May 20, 2021 Merrimack Valley Planning Commission (MVPC) meetings (all held Virtually due to COVID-19 Virus restrictions)
� May 5, 2021 Merrimack Valley DPW/ Stormwater Collaborative meeting (held Virtually due to COVID-19 Virus restrictions)
The
above meetings were held Virtually due to COVID-19 restrictions.
Page
intentionally left blank.
Adjustments
Minor adjustments to the TIP do not require formal MPO action and can be made via the administrative action of the Merrimack Valley MPO. These minor adjustments are limited to:
� Changing the scope and description of a project as long as they are minor changes;
� Changing funding amounts that are less than a ten percent increase in project cost if project cost is more than $5 million dollars;
� Changing funding amounts that are an increase of less than $500,000 if project cost is $5 million dollars or less;
� Changing funding sources.
Amendments
Major changes continue to require MPO action through the formal amendment process. Major changes would require a twenty-one-day public review and comment period that includes a public hearing. These changes include, but are not limited to:
� Moving a currently programmed project earlier or later than an originally programmed year;
� MassDOT Office of Transportation Planning (OTP) approved ten percent or more increases, or decreases, in the construction cost estimate for a project costing more than $5 million dollars;
� MassDOT OTP approved project cost increase, or decrease, of $500,000 or more, in the construction cost estimate for a project costing $5 million dollars or less;
� Adding a new project;
� Deleting a project;
� Major change in project scope large enough to necessitate an additional review by MassDOTs Project Review Committee (PRC) typically accompanied by major project cost change;
� Exceptions
Although the MVMPO typically holds a 21-day public comment period for amendments, in the event of extenuating circumstances beyond the agencys control, the comment period may be shortened or waived in consultation with FHWA Division Office and/or the FTA Regional Office. Additionally, MassDOT may make exceptions to the procedures outlined above and treat amendments as adjustments and/or adjustments as administrative modifications, but these exceptions will also require coordination with and concurrence by MassDOTs federal partners and the affected MPO.
The above Adjustments and Amendments align with MassDOTs definitions of Adjustments and Amendments. One difference from the MassDOT State Transportation Improvement Program (STIP) Project Revision Definitions and Procedures is that MassDOT defines an Administrative Modification: A revision to the STIP that is minor enough in nature to require neither a public process nor FHWA/FTA approval, but that does involve a notification to federal partners.
This document does not have an Administrative Modification. The only items that MassDOT defines as Administrative Modifications are minor changes to Project Description and a change in any item listed in the Additional Information column of the STIP not covered in any Amendment or Adjustment procedure. The MVMPO must use the Project Descriptions provided by MassDOT, the only time a Project Description changes is if MassDOT changes it, this would be considered an Adjustment to this document. Any changes to Additional Information not listed in the Amendment/ Adjustment procedures above would be coordinated with MassDOT and would not require action by the MVMPO.
SAFETEA-LU contained a number of earmarked transportation projects that were to receive federal funding. Specific funding amounts were obligated to each of these projects, but no additional funding was included in SAFETEA-LU to complete them. Consequently, states with these projects must implement them within the annual federal authorization limits established in the legislation. The Merrimack Valley region contains eleven such projects which are shown below along with their status:
Highway High Priority Projects |
Status |
Amesbury/Newburyport Rehabilitation of I-95 Whittier Bridge |
Project Complete |
Andover Design, Engineering and Construction at I-93 The Junction Interchange, (Andover, Tewksbury, and Wilmington) |
Project Deactivated |
Haverhill Construct Haverhill intermodal center access and vehicle capacity improvements. |
Project Complete |
Lawrence Design and construct Canal and Union Street Corridor improvements. |
Project Complete |
Lawrence Construct access improvements to the Lawrence Gateway Project. |
Project Complete |
Methuen Design, engineering and construction of Methuen Rotary alternative at I-93 and Routes 110 and 113. |
Project Complete |
Newbury Rehabilitation and paving of Parker River Road |
Project Complete |
North Andover Improvements to Mass. Ave., Andover St., Osgood St., Salem St and Johnson St. in the Old Town Center of North Andover |
Project Complete |
Parker River National Wildlife Refuge Preliminary engineering for Rehabilitation and paving of Sunset Drive in National Wildlife Refuge |
Project Complete |
Salisbury to Boxford Design, Engineer, Permit and Construct Border to Boston Bikeway rail trail project |
Salisbury Section under Construction. Remaining sections under Design. |
Transit Projects for Bus and Bus-Related Facilities and Clean Fuels Grant Program |
Status |
Haverhill Design and Construct Intermodal Transit Parking Improvements. |
Project Complete (see above) |
Lawrence Gateway Intermodal and Quadrant Area Reuse Project. |
Project Complete (see above) |
Newburyport Design and Construct Intermodal Facility |
Project Complete |
Regionally Significant Projects
Community |
Project |
North Andover |
Corridor Improvements on Route 114, between Route 125 (Andover Street) & Stop & Shop Driveway (# 608095) |
Advance Construction is a Federal-aid fund management tool, which as described by the Federal Highway Administration website:
allows states to begin a project even in the absence of sufficient Federal-aid obligation authority to cover the Federal share of project costs. It is codified in Title 23, Section 115. Advance construction eliminates the need to set aside full obligational authority before starting projects At some future date when the state does have sufficient obligational authority, it may convert an advance-constructed project to a Federal-aid project by obligating the permissible share of its Federal-aid funds and receiving subsequent reimbursements.
In other words, the state pays for the project with non-Federal-aid funds to begin with and can later seek reimbursement of the Federal share of the funding categorys project cost by obligating Federal-aid funding in future years.
Projects must meet the following criteria before they can be designated to use the Advanced Construction (AC) funding mechanism:
1. The projects estimated Federal participating cost exceeds the total regional annual target (i.e. sum of HSIP, CMAQ, TA and Non HSIP/CMAQ/TA), and
2. Construction, based on an engineering review of the project, will take place during all the years for which federal funding is programmed.
The following projects are programmed in the FFY 2022 to 2026 TIP using this Advance Construction (AC) method:
Haverhill-Bridge Replacement, H-12-039, I-495 (NB & SB) over Merrimack River
North Andover-Corridor Improvements on Route 114, between Rt 125 (Andover St) & Stop & Shop Driveway
Haverhill-Bridge Replacement, H-12-040, I-495 (NB & SB) over Merrimack River
Haverhill-Bridge Replacement, H-12-007 & H-12-025, Bridge Street (SR 125) over Merrimack River and the Abandoned B&M RR (Proposed Bikeway)
Andover-Bridge Rehabilitation, A-09-036, I-495 over St 28 (SB), A-09-037, I-495 over B&M and MBTA, A-09-041, I-495 over St 28 (NB)
Lawrence-Lawrence-Manchester Rail Corridor (LMRC) Rail Trail
Salisbury-Reconstruction of Route 1 (Lafayette Road)
Projects listed in the TIP must show the sources of funding that will be used to complete the project. The projects in the FFYs 2022 to 2026 TIP are slated to use funding from the following Federal-aid funding programs identified in the FAST Act federal transportation funding authorization extended through September 2021. Please note that in some cases Federal-aid funding is from older funding programs established in earlier legislation such as SAFETEA-LU and MAP-21. Projects may also receive non-Federal Aid funding which is shown in the project listings.
Bridge Replacement and Rehabilitation ((BR) (continued in FAST Act))-funds replacement and repair of Structurally Deficient or unsafe bridges in urban and rural areas on any public road. Bridges can be on the federal aid system (BR ON) or off system (BR OFF).
Funding: Federal 80%, State 20%
Congestion Mitigation and Air Quality Improvement Program ((CMAQ) (continued in FAST Act)�funds projects that reduce congestion and improve air quality.
Funding: Federal 80%, State 20%
High Priority Projects (HPP) (Carryover from SAFETEA-LU)�funds up to 80% of the costs of specific transportation projects identified in SAFETEA-LU. These projects have a separate allocation, but do not receive additional funds, and are therefore subject to the states federal authorization limit.
Funding: Federal 80%, State 20%
Highway Safety Improvement Program ((HSIP) (continued in FAST Act))-funds safety improvement projects at high crash locations and Railway-Highway Crossings.
Funding: Federal 90%, State 10%
National Highway Performance Program (NHPP) (continued in FAST Act)-funds projects on all National Highway System Roadways.
Funding: Varies, generally Federal 80%, State 20%, but for the Interstate System, Federal 90%, State 10%
Non-Federal Aid (NFA)-funds construction, reconstruction, and improvement projects on roads and bridges in urban and rural areas.
Funding: State 100%
(Transportation Bond Bill), or Private 100%
Transportation Funding Programs-Highway Projects (Continued)
Surface Transportation Block Grant Program (STBG) (STP) (also known as the Surface Transportation Program (STP) from previous legislation)-funding for any Federal-aid highway, bridge and tunnel projects on any public road, pedestrian and bicycle infrastructure, and transit capital projects, including intercity bus terminals.
STP Enhancements ((STP E) ((SAFETEA-LU; not continued in MAP-21)) a portion of Surface Transportation Program funding for enhancement projects chosen by states and localities.
Funding: Federal 80%, State 20%
Transportation Alternatives Program (TAP) (MAP-21, replaced in FAST Act with Transportation Alternatives (TA) set aside of STBG funds)-funds for projects which can be defined as transportation alternatives including bicycle and pedestrian facilities, enhanced mobility, community improvements, environmental mitigations, and various other types of transportation alternatives as defined in FAST Act.
Funding: Federal 80%, State 20%
The Merrimack Valley Regional Transit Authority (MVRTA) provides local and intercity fixed-route bus service, paratransit service for seniors and persons with disabilities, flexible Ring and Ride service is provided in some communities with no fixed route service, commuter service to Boston, one weekday employment bus route from Lawrence to major employers of Raytheon and IRS, and one seasonal bus route to Salisbury and Hampton beaches.
Prior to the COVID-19 Pandemic, in FY 2019 (July 1, 2018 to June 30, 2019) the MVRTA fixed route services ridership was over 1.9 million, with an additional 44,040 passengers on special routes. EZ Trans paratransit ridership was 60,397 ADA and 6,817 Non-ADA. The commuter buses to Boston carried 60,822 passengers and Ring and Ride provided service to 10,868 passengers, for a total of nearly 2.08 million rides provided by MVRTA in FY 2019.
Federal, State and local subsidies provide the majority of the funding for the MVRTA, for both capital and operating expenses. Any Federal funding and its match, generally State funding, is required to be listed in this TIP.
Projects from the following Federal-aid (FAST Act extended through September 2021) and non-Federal-aid funding categories are shown in the FFY 2022 to 2026 TIP.
Federal Transit Funding
Section 5307 (Capital and Planning) (continued in FAST Act) funds routine capital projects and planning assistance in urban areas. This is an urban formula grant program for MVRTA Preventative Maintenance and ADA costs.
Funding: Federal 80%, State 20% (Bond Issue Funds) (capital and planning expenses)
State funding for the MVRTAs operating budget is provided through an agreement with the Transit Division of MassDOT. Local funds are derived from community assessments based on the number of route miles and special services operated within each community.
The Merrimack Valley Planning Commission will provide the 20% match for the planning activities it will conduct for the Merrimack Valley Regional Transit Authority under its Section 5307 transit planning contract with the Authority.
Section 5309 (continued in FAST Act)-funds capital projects in urban areas which can be characterized as major capital investments in public transportation equipment and facilities. This is a discretionary grant program.
Funding: Federal 80%, State 20% (Transportation Bond Issue)
Section 5310 (continued in FAST Act))-provides capital funds, through the State, to private non-profit corporations and organizations to assist them in providing transportation services to meet the special needs of elderly and disabled persons.
Funding: Federal 80%, Funding Applicant 20%
Section 5339 (continued in FAST Act)-provides capital funds, through the State, for bus and bus related equipment and facilities.
Funding: Federal 80%, Funding Applicant 20%
State Transit Funding
Operating Assistance
State Contract Assistance (SCA) annual State funding which can be used for Federal operating expenses and as part of the match for Federal transit operating funding programs.
State Capital Assistance
Regional Transit Authority Capital Assistance Program (RTACAP) annual State funding which can be used to provide the match for Federal transit capital funding programs.
Organization of Project Listings Highway Projects
The TIP includes sections that identify the MPOs priority road and bridge projects using a format prescribed by MassDOTs Office of Transportation Planning. MassDOT is aligning the FFYs 2022 to 2026 Statewide Transportation Improvement Program (STIP) with the MassDOT Capital Investment Plan (CIP). The CIP identifies three capital planning priorities: reliability, modernization and expansion investments. The STIP will now align program names with CIP investment priorities as follows:
Reliability
� Bridge program (including investments in inspections, systematic maintenance, on-system NHS bridges, on-system non-NHS bridges, and off-system bridges)
� Interstate pavement program
� Non-Interstate DOT pavement program
� Roadway improvements program
� Safety improvements program
Modernization
� ADA retrofits program
� Intersection improvements program
� Intelligent Transportation Systems program
� Roadway reconstruction program
Expansion
� Bicycles and Pedestrians program
� Capacity program
For the FFYs 2022 to 2026 TIP, the Regional Target funding amounts, distributed via statewide formula to the regions across the state, are initially programmed by the regions as STBG (also known as STP) funding category projects and MassDOT will inform regions if projects are to be partitioned by the HSIP, CMAQ and TAP categories.
Section 1A / Regionally Prioritized Projects
� Federal-Aid STBG Projects Using MVMPO Target Authority (STBG)
� Federal-Aid HSIP Projects Using MVMPO Target (HSIP)
� Federal-Aid CMAQ Projects Using MVMPO Target (CMAQ)
�
Federal-Aid TAP (now set aside of STBG
funding) Projects Using MVMPO Target (TAP)
Section 1B / Earmark or Discretionary Grant Funded Projects (Provided by MassDOT)
� Federal-Aid Earmark or Discretionary Grant Funded Projects
Section 2A / State Prioritized Reliability Projects (Provided by MassDOT)
� Bridge Program/ Inspections
� Bridge Program/ Off-System
� Bridge Program/ On-System (NHS)
� Bridge Program/ On-System (Non-NHS)
� Bridge Program/ Systematic Maintenance
� Interstate Pavement
� Non-Interstate Pavement
� Roadway Improvements
� Safety Improvements
Section 2B / State Prioritized Modernization Projects (Provided by MassDOT)
� ADA Retrofits
� Intersection Improvements
� Intelligent Transportation Systems
� Roadway Reconstruction
Section 2C / State Prioritized Expansion Projects (Provided by MassDOT)
� Bicycles and Pedestrians
� Capacity
Section 3 / Planning / Adjustments / Pass-throughs (Provided by MassDOT)
� Planning / Adjustments / Pass-throughs
Section 4 / Non-Federally Aided Projects (Provided by MassDOT)
� Non-Federal Aid
Each highway project in the TIP contains the following information:
Amendment/Adjustment Type used to identify the type of amendment when changes are made to the document.
STIP Program-STIP program names as defined in the Organization of Highway Project Listings section above.
MassDOT Project ID-project identification numbers given by MassDOT for each highway and bridge project.
MPO-identifies the Metropolitan Planning Organization within which the project is located.
Municipality Name-identifies the community where the project is located.
MassDOT Project Description-includes the community, or communities, in which the project is located and a brief description of work to be funded under the project. This description is exactly the same as MassDOT has input to its project information pages.
MassDOT District-MassDOT highway district number (Merrimack Valley MPO is part of District 4);
Funding Source-abbreviation for the funding category from which funding is expected. (Funding categories and abbreviations are explained at the beginning of Part A.8.);
Total Programmed Funds-estimated cost of project in Fiscal Year in which advertising is expected; *
Federal Funds-portion of Total Programmed Funds provided by Federal Funding;
Non-Federal Funds-portion of Total Programmed Funds not provided by Federal Funding, but required as matching funds in order to receive Federal Funds;
Additional Information-a) Planning / Design / Construction; b) total project cost and funding sources used; c) advance construction status; d) MPO project score; e) name of entity receiving a transfer; f) name of entity paying the non-State Non-Federal match; g) earmark details; h) TAP project proponent; i) other information.
* Inflation increases project costs and therefore the
project costs have been increased by 4% each future year of the TIP.
Organization of Project Listings Transit Projects
Each transit project in the TIP contains the following information:
Division ID-Transit Project ID from MassDOT
Agency-MVRTA (Merrimack Valley Regional Transit Authority) is the regional transit authority;
Project Title-the project title from MassDOT
Federal Funds-Portion of Total Programmed Funds provided by Federal Funding;
RTACAP-Regional Transit Authority State Capital Assistance-portion of Total Programmed Funds not provided by Federal Funding, but required as matching funds in order to receive Federal Funds, coming from State source;
SCA-State Contract Assistance-portion of Total Programmed Funds not provided by Federal Funding, but required as matching funds in order to receive Federal Funds, coming from State source;
TDC-Transportation Development Credits, and
Local Funds-portion of Total Programmed Funds not provided by Federal Funding but required as matching funds in order to receive Federal Funds, coming from local funding sources other than State funding sources.
Total-estimated total cost
of project.
TIP FFYs 2022 to 2026 Transit Projects
2022
FTA Section 5307
Division ID |
Agency |
Project Title |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
RTD0009672 |
MVRTA |
MVRTA Operating Assistance |
$644,945 |
$0 |
$644,945 |
$0 |
$0 |
$1,289,890 |
RTD0009669 |
MVRTA |
MVRTA Preventative Maintenance |
$2,889,070 |
$0 |
$722,265 |
$0 |
$0 |
$3,611,335 |
RTD0009671 |
MVRTA |
MVMPO Short Range Transit Planning |
$80,000 |
$0 |
$0 |
$0 |
$20,000 |
$100,000 |
RTD0009673 |
MVRTA |
MVRTA Replace 9 Model Yr 2009 35 ft. buses delivery 2022 |
3,269,223 |
1,188,807 |
|
|
|
4,458,030 |
RTD0010053 |
MVRTA |
MVRTA HQ Facility Repairs |
$545,600 |
$136,400 |
$0 |
$0 |
$0 |
$682,000 |
RTD0009680 |
MVRTA |
MVRTA Replace 1 model year 2016 supervisory vehicle |
39,095 |
9,775 |
|
|
|
$48,870 |
RTD0009670 |
MVRTA |
MVRTA ADA Paratransit Service |
$1,441,305 |
$0 |
$360,325 |
$0 |
$0 |
$1,801,630
|
RTD0010107 |
MVRTA |
MVRTA Riverbank Stabilization Construction |
$2,036,800 |
$509,200 |
|
|
|
$2,546,000 |
|
|
FTA Section 5307 Totals |
$10,946,038 |
$1,844,182 |
$1,727,535 |
|
$20,000 |
$14,537,755 |
TIP FFYs 2022 to 2026 Transit Projects
2022 (Cont.)
Non-Federal Aid
Division ID |
Agency |
Project Title |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
RTD0010061 |
MVRTA |
MVRTA Acquire Bus Plus Payment Software |
|
$40,735 |
|
|
|
$40,735 |
S12109 |
MVRTA |
MVRTA Flex to FTA to Repower five (5) 2015 Transit Buses (STBG MATCH ON HWY TIP PROJECT #S12109) |
$251,350** |
|
|
$62,835* |
|
$251,350* |
S12110 |
MVRTA |
MVRTA Flex to FTA to Repower five (5) 2016 Transit Buses (STBG MATCH ON HWY TIP PROJECT #S12110) |
$262,850** |
|
|
$65,710* |
|
$262,850* |
S12111 |
MVRTA |
MVRTA Flex to FTA to Upgrade CAD/AVL and Automated Vehicle Announcement (AVA) (STBG MATCH ON HWY TIP PROJECT #S12111) |
$756,970** |
|
|
$189,240* |
|
$756,970* |
|
|
Non-Federal Aid Totals |
|
$40,735 |
|
$317,785* |
|
$40,735* |
* TDC (Transportation Development Credits) are not included in totals.
** The Federal dollars are being Flexed to FTA from Highway
Regional Target Funding
TIP FFYs 2022 to 2026 Transit Projects
2023
FTA Section 5307
Division ID |
Agency |
Project Title |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
RTD0009674 |
MVRTA |
MVRTA Preventative Maintenance for service |
$2,984,410 |
$0 |
$746,100 |
$0 |
$0 |
$3,730,510 |
RTD0009675 |
MVRTA |
MVRTA Operating Assistance for service |
$739,365 |
$0 |
$739,365 |
$0 |
$0 |
$1,478,730 |
RTD0009676 |
MVRTA |
MVRTA ADA Paratransit Service |
$1,488,870 |
$0 |
$372,220 |
$0 |
$0 |
$1,861,090 |
RTD0009677 |
MVRTA |
MVRTA Replace 8 Model Yr 2011 35 ft. buses delivery 2023 |
$3,507,520 |
$876,880 |
|
$0 |
$0 |
$4,384,400 |
RTD0009678 |
MVRTA |
MVRTA Replace 6 Model Yr 2017 Type E-2 vans delivery 2023 |
$234,810 |
$234,810 |
|
$0 |
$0 |
$469,620 |
RTD0009679 |
MVRTA |
MVMPO Short Range Transit Planning |
$80,000 |
$0 |
|
$0 |
$20,000 |
$100,000 |
RTD0009687 |
MVRTA |
MVRTA Replace 1 Model Year 2017 Supervisory Vehicle |
$40,265 |
$10,070 |
$0 |
$0 |
$0 |
$50,335 |
|
|
FTA Section 5307 Totals |
$9,075,240 |
$1,121,760 |
$1,857,685 |
|
$20,000 |
$12,074,685 |
TIP FFYs 2022 to 2026 Transit Projects
2023 (Cont.)
Non-Federal Aid
Agency |
Project Description |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
MVRTA |
MVRTA Flex to FTA to Replace Yr 2011 Buses with New Clean Diesel Buses Order 1/2022 Delivery 6/2023 (6 of 8) (STBG MATCH ON HWY TIP PROJECT #S12107) |
$2,386,560* |
$596,640 |
|
|
|
$2,983,200 |
MVRTA |
MVRTA Flex to FTA to Replace Yr 2011 Buses with New Hybrid Buses Order 1/2022 Delivery 6/2023 (2 of 8) (STBG MATCH ON HWY TIP PROJECT #S12108) |
$1,120,960* |
$280,240 |
|
|
|
$1,401,200 |
|
Non-Federal Aid Totals |
|
$876,880 |
|
|
|
|
* The Federal dollars are being Flexed to FTA from Highway Regional Target Funding
TIP FFYs 2022 to 2026 Transit Projects
2024
FTA Section 5307
Division ID |
Agency |
Project Title |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
RTD0009688 |
MVRTA |
MVRTA Replace 1 model year 2018 Supervisory Vehicle |
$41,475 |
$10,370 |
$0 |
$0 |
$0 |
$51,845 |
RTD0009681 |
MVRTA |
MVRTA Replace 8 model yr 2012 35 ft. buses delivery 2024 (8 of 8) |
$2,351,600 |
$2,351,600 |
|
|
|
$4,703,200 |
RTD0009682 |
MVRTA |
MVRTA Preventative Maintenance for service |
$2,894,615 |
$0 |
$723,650 |
$0 |
$0 |
$3,618,265 |
RTD0009683 |
MVRTA |
MVRTA Operating Assistance for Service |
$714,840 |
|
$714,840 |
|
|
$1,429,680 |
RTD0009684 |
MVRTA |
MVRTA ADA paratransit service |
$1,444,205 |
$0 |
$361,050 |
$0 |
$0 |
$1,805,255 |
RTD0009685 |
MVRTA |
MVMPO Short Range Transit Planning |
$80,000 |
$0 |
$0 |
$0 |
$20,000 |
$100,000 |
|
|
|
|
|
|
|
|
|
|
|
FTA Section 5307 Totals |
$7,526,735 |
$2,361,970 |
$1,799,540 |
$0 |
$20,000 |
$11,708,245 |
TIP FFYs 2022 to 2026 Transit Projects
2025
FTA Section 5307
Division ID |
Agency |
Project Title |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
RTD0009689 |
MVRTA |
MVMPO Short Range Transit Planning |
$80,000 |
$0 |
$0 |
$0 |
$20,000 |
$100,000 |
RTD0009690 |
MVRTA |
MVRTA Preventative Maintenance for service |
$2,952,505 |
$0 |
$738,125 |
$0 |
$0 |
$3,690,630 |
RTD0009691 |
MVRTA |
MVRTA Operating Assistance for service |
$729,135 |
$0 |
$729,135 |
$0 |
$0 |
$1,458,270 |
RTD0009692 |
MVRTA |
MVRTA ADA Paratransit Service |
$1,473,090 |
$0 |
$368,275 |
$0 |
$0 |
$1,841,365 |
RTD0009693 |
MVRTA |
MVRTA Replace 1 Model Year 2019 Supervisory Vehicle |
$42,720 |
$10,680 |
$0 |
$0 |
$0 |
$53,400 |
|
|
FTA Section 5307 Totals |
$5,277,450 |
$10,680 |
$1,835,535 |
$0 |
$20,000 |
$7,143,665 |
TIP FFYs 2022 to 2026 Transit Projects
2026
FTA Section 5307
Division ID |
Agency |
Project Title |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
|
RTD0010055 |
MVRTA |
MVRTA Preventative Maintenance for Service |
$3,041,080 |
$0 |
$769,270 |
$0 |
$0 |
$3,810,350 |
|
RTD0010057 |
MVRTA |
MVRTA ADA Paratransit Service |
$1,517,285 |
$0 |
$349,320 |
$0 |
$0 |
$1,866,605 |
|
RTD0010058 |
MVRTA |
MVMPO Short Range Transit Planning |
$80,000 |
$0 |
$0 |
$0 |
$20,000 |
$100,000 |
|
RTD0010059 |
MVRTA |
MVRTA Operating Assistance for Service |
$751,010 |
$0 |
$751,010 |
$0 |
$0 |
$1,502,020 |
|
RTD0010060 |
MVRTA |
MVRTA Replace 1 Model Yr 2020 Supervisory Vehicle |
$44,000 |
$11,000 |
|
|
|
$55,000 |
|
|
|
FTA Section 5307 Totals |
$5,433,375 |
$11,000 |
$1,869,600 |
$0 |
$20,000 |
$7,333,975 |
|
Summary of Highway Projects by Town
(2022 to 2026 Regional Target Funds)
Year (s) Programmed |
City / Town |
Project Description |
Total Cost Programmed |
2022 |
Lawrence |
Lawrence-Intersection Improvements at Merrimack Street and South Broadway (Route 28) (# 609509) |
$1,502,354 |
2022 |
Lawrence |
Lawrence-Intersection Reconstruction at Marston Street & East Haverhill Street (# 610923) |
$1,658,011 |
2023 |
Methuen |
Methuen-Intersection Improvements at Riverside Drive and Burnham Road (# 610658) |
$967,200 |
2024-2026 |
North Andover |
North Andover-Corridor Improvements on Route 114, between Route 125 (Andover Street) & Stop & Shop Driveway (# 608095) * |
$25,392,871* |
2023-2024 |
Salisbury |
Salisbury-Reconstruction of Route 1 (Lafayette Road) |
$18,214,824 |
2022 |
MVRTA |
MVRTA Flex to FTA to Replace Yr 2011 Buses with New Clean Diesel Buses Order 1/2022 Delivery 6/2023 (6 of 8) (# S12107) |
$2,983,200 |
2022 |
MVRTA |
MVRTA Flex to FTA to Replace Yr 2011 Buses with New Hybrid Buses Order 1/2022 Delivery 6/2023 (2 of 8) (# S12108) |
$1,401,200 |
2022 |
MVRTA |
MVRTA Flex to FTA to Repower five (5) 2015 Transit Buses (# S12109) |
$314,185 |
2022 |
MVRTA |
MVRTA Flex to FTA to Repower five (5) 2016 Transit Buses (# S 12110) |
$328,560 |
2022 |
MVRTA |
MVRTA Flex to FTA to Upgrade CAD/AVL and Automated Vehicle Announcement (AVA) (# S12111) |
$946,210 |
* North Andover Route 114 is ACd FFY 2024 to 2026, FFY 2027 = $ 10,001,905, Total Project Cost =$35,394,776
Summary of Programmed Highway Funds by Town
(2022 to 2026 Regional Target Funds)
Project Description |
Total Cost Programmed |
Lawrence Total |
$3,160,365 |
Methuen Total |
$967,200 |
North Andover Total |
$25,392,871 |
Salisbury Total |
$18,214,824 |
MVRTA Total |
$5,973,355 |
Regional Total |
$53,708,615 |
Summary of Highway Projects by Town
(2022 to 2026 Statewide and Regional Target Funds)
Year (s) Programmed |
City / Town |
Project Description |
Total Cost Programmed |
2024-2026 |
Andover |
Andover-Bridge Rehabilitation, A-09-036, I-495 over St 28 (SB), A-09-037, I-495 over B&M and MBTA, A-09-041, I-495 over St 28 (NB) (# 606522) |
$64,225,138* |
2025 |
Georgetown / Boxford |
Georgetown/ Boxford-Border to Boston Trail, from Georgetown Road to West Main Street (Route 97) (# 607541) |
$2,714,316 |
2025 |
Georgetown / Newbury |
Georgetown/ Newbury-Border to Boston Trail, (Northern Georgetown to Byfield Section) (# 607542) |
$5,685,060 |
2024-2026 |
Haverhill |
Haverhill-Bridge Replacement, H-12-007 & H-12-025, Bridge Street (SR 125) over the Merrimack River and the Abandoned B&M RR (Proposed Bikeway) (# 605304) |
$57,381,766* |
2022 |
Haverhill |
Haverhill-Bridge Replacement, H-12-039, I-495 (NB & SB) over Merrimack River (# 605306) |
$12,994,233* |
2024-2026 |
Haverhill |
Haverhill-Bridge Replacement, H-12-040, I-495 (NB & SB) over Merrimack River (# 609466) |
$78,161,628* |
* Andover (# 606522) is Advance Constructed (AC) FFY 2024 to 2028, Total Project Cost =$186,921,000
Haverhill (# 605304) is AC FFY 2024 to 2028, Total Project Cost = $112,166,208
Haverhill (# 605306) is AC FFY 2018 to 2022, Total Project Cost = $108,833,832
Haverhill (# 609466) is AC FFY 2024 to 2027, Total Project Cost = $99,783,090
Summary of Highway Projects by Town
(2022 to 2026 Statewide and Target Funds) (Cont.)
Year (s) Programmed |
City / Town |
Project Description |
Total Cost Programmed |
2026 |
Lawrence |
Lawrence-Bridge Replacement, L-04-012, Short Street over Spicket River (# 612074) |
$3,402,326 |
2025 |
Lawrence |
Lawrence-Community Day Arlington Improvements (612002) |
$1,611,774 |
2022 |
Lawrence |
Lawrence-Intersection Improvements at Merrimack Street and South Broadway (Route 28) (# 609509) |
$1,502,354 |
2022 |
Lawrence |
Lawrence-Intersection Reconstruction at Marston Street & East Haverhill Street (# 610923) |
$1,658,011 |
2023-2024 |
Lawrence |
Lawrence-Lawrence Manchester Rail Corridor (LMRC) Rail Trail (# 608930) |
$21,416,304 |
2023 |
Methuen |
Methuen-Intersection Improvements at Riverside Drive and Burnham Road (# 610658) |
$967,200 |
2022 |
Newbury/ Newburyport/ Salisbury |
Newbury/ Newburyport/ Salisbury-Resurfacing and related work on Route 1 (# 608494) |
$9,722,950 |
Summary of Highway Projects by Town
(2022 to 2026 Statewide and Target Funds) (Cont.)
Year (s) Programmed |
City / Town |
Project Description |
Total Cost Programmed |
2024-2026 |
North Andover |
North Andover-Corridor Improvements on Route 114, between Route 125 (Andover Street) & Stop & Shop Driveway (# 608095) * |
$25,392,871* |
2023 |
Rowley |
Rowley-Safety Improvements at Route 1, Central and Glen Streets (# 609392) |
$1,486,378 |
2023-2024 |
Salisbury |
Salisbury-Reconstruction of Route 1 (Lafayette Road) (# 602202) |
$18,214,824 |
2022 |
MVRTA |
MVRTA Flex to FTA to Replace Yr 2011 Buses with New Clean Diesel Buses Order 1/2022 Delivery 6/2023 (6 of 8) (# S12107) |
$2,983,200 |
2022 |
MVRTA |
MVRTA Flex to FTA to Replace Yr 2011 Buses with New Hybrid Buses Order 1/2022 Delivery 6/2023 (2 of 8) (# S12108) |
$1,401,200 |
2022 |
MVRTA |
MVRTA Flex to FTA to Repower five (5) 2015 Transit Buses (# S12109) |
$314,185 |
2022 |
MVRTA |
MVRTA Flex to FTA to Repower five (5) 2016 Transit Buses (# S 12110) |
$328,560 |
2022 |
MVRTA |
MVRTA Flex to FTA to Upgrade CAD/AVL and Automated Vehicle Announcement (AVA) (# S12111) |
$946,210 |
* North Andover Route 114 is ACd FFY 2024 to 2026, FFY 2027 = $ 10,001,905, Total Project Cost =$35,394,776
Summary of Programmed Highway Funds by Town
(2022 to 2026 Statewide and Regional Target Funds)
Project Description |
Total Cost Programmed |
|
|
Andover Total |
$64,225,138 |
Boxford Total |
$1,357,158 |
Georgetown Total |
$4,199,688 |
Haverhill Total |
$148,537,627 |
Lawrence Total |
$29,590,769 |
Methuen Total |
$967,200 |
Newbury Total |
$6,083,513 |
Newburyport Total |
$3,240,983 |
North Andover Total |
$25,392,871 |
Rowley Total |
$1,486,378 |
Salisbury Total |
$21,455,807 |
MVRTA Total |
$5,973,355 |
Regional Total |
$312,510,487 |
Page intentionally left blank.
The TIP must be financially constrained, meaning projects included in the TIP must have an identified funding source. Funding levels for Federal Fiscal Years 2022 to 2026 have been developed cooperatively between the State and the MPOs as part of the TIP development process. The following tables depict the resulting financial plan for each of the five fiscal years. MassDOT receives a funding Apportionment or estimate of total available federal funding from the Federal Highway Administration (FHWA) then Congress looks at the budget each year and places a limit on how much can be spent from the expected highway Apportionment resulting in the obligation limitation MassDOT can spend in federal funding each year. The Proposed Base Obligation Authority estimated is based on a 2.1% growth rate from the actual FFY 2021 apportionment and average Fast Act Obligation Authority of 91% through FFY 2020. This estimated Proposed Base Obligation Authority is less than the current estimated Base Obligation Authority, the MassDOT Highway Division programs are being revised based on new Accelerated Bridge Program (ABP) Grant Application Notes (GANs) repayment schedule and the proposed lower Obligation Authority, no changes are being made to the MPO TIP Targets for FFY 2022 to 2025. This estimated Base Obligation Authority is listed first to which is added a Planned redistribution request estimated to be $50,000,000 each year of the TIP. (Toward the end of the FFY any state that has not spent their Federal Obligation Authority returns that authority, and the Federal government redistributes those funds to the other states.) The Total estimated Federal Funds available to Massachusetts is estimated to be between approximately 667 million dollars and 720 million dollars for each of FFYs 2022 to 2026. The State then subtracts annual debt service payments for the Accelerated Bridge Program (ABP) Grant Application Notes (GANs) which range from 82 million dollars to more than 133 million dollars for each year over the five years of the TIP. Resulting in the Total non-earmarked funding available to the State ranging from 581 million dollars to 599 million dollars depending on the ABP GANS repayment schedule.
The funding for regional priorities remains 198.6 million dollars in 2022, 203 million dollars in 2023, 205.6 million dollars in 2024, and 200.8 million dollars in 2025. The amount available to the regions is less in 2026, in line with the estimated reduced base Obligation Authority, as well as the increase in the ABP GANS repayment in 2026, to 195.6 million dollars. The State generally provides the 20% match required for the Federal funds resulting in estimated funds ranging from approximately 244.5 million dollars to approximately 257 million dollars available for regional funding priorities for each of the five years of the TIP.
This funding is then allocated to MPOs based upon the existing Massachusetts Association of Regional Planning Agencies (MARPA) TIP target distribution formula. This MARPA Formula is based mainly on each MPOs road mileage and population. The MVMPOs share is 4.4296%, resulting in the total funding available for MVMPO regional priorities with the 20% State match to be: $10,998,131 in FFY 2022; $11,238,340 in FFY 2023; $11,385,638 in FFY 2024: $11,119,839 in FFY 2025 and $10,831,078 in FFY 2026.
In FFY 2017 MassDOT ended funding for the regional major infrastructure program after the I-91 Viaduct in Springfield project had been completed. These funds will be reallocated to the Regional Target program for prioritization by MPOs across the state.
Inflation increases project costs and therefore project costs have been increased 4% per year.
.
The following table shows the total federal programmed amounts in this TIP for each of the five years covered in this document. The funding summaries below show the total Operating and Maintenance costs versus Capital and Other costs, for each year of the TIP. A fiscal constraint finding for the State Transportation Improvement Program will include the cost of operating and maintaining the existing MVMPO transportation system.
Merrimack Valley Metropolitan Planning Organization
FFY 2022 to 2026 Transportation Improvement Program
(FHWA related funding categories only)
Total Costs including Federal and State Match*
Figures include Federal Aid target program & statewide funding
Fiscal Year |
Federal Programmed Operating/ Maintenance Costs*(inc. Match) |
Federal Programmed Capital and Other Costs*(inc. Match) |
Total Federal + Match Programmed* |
Total Federal + Match Estimated Available Funds* |
2022 |
$31.85 |
$0.00 |
$31.85 |
$33.72 |
2023 |
$12.72 |
$11.49 |
$24.21 |
$24.21 |
2024 |
$61.15 |
$9.93 |
$71.08 |
$71.08 |
2025 |
$61.27 |
$8.40 |
$69.67 |
$69.67 |
2026 |
$115.70 |
$0.00 |
$115.70 |
$115.70 |
* Millions of dollars
The financial plan contained herein is financially constrained and indicates that the Merrimack Valley Metropolitan Planning Organizations FFYs 2022 to 2026 TIP reflects an emphasis on the maintenance and operation of the current roadway and bridge system with the ability to provide additional capital improvements. Only projects for which funds can be expected have been included.
Appendix B of this document includes a
list of Non-federal-aid transportation projects in the region. The projects
listed in Appendix B are an integral part of the planning, programming, and
priority setting process of the MVMPO but have no available funding source.
The following tables contain a breakdown of the project cost totals and federal aid cost portions by federal aid funding categories for each fiscal year and the expected available resources to cover the cost.
Cost Estimates and Available Resources
Summary by Funding Category
Highway Projects Federal Fiscal Year 2022
Highway FFY 2022 |
Estimated Needs MVMPO (in 1000s) Federal Portion of Cost |
Estimated Needs MVMPO (in 1000s) Total Project Cost |
Available Resources MVMPO Projects (in 1000s) (From Region Target if not Statewide Category) |
Regional Target Congestion Mitigation/AQ Program (CMAQ) |
$0 |
$0 |
$0 |
Regional Target Highway Safety Program (HSIP) |
$0 |
$0 |
$0 |
Regional Target Surface Transportation Block Grant Program (STBG) |
$7,306.98 |
$9,133.72 |
$10,998.13 |
Regional Target Subtotals |
$7.306.98 |
$9,133.72 |
$10,998.13 |
Statewide Bridge On-System NHS (NHPP) |
$10,395.39 |
$12,994.23 |
$12,994.23 |
Statewide Non-Interstate Pavement (NHPP) |
$7,778.36 |
$9,722.95 |
$9,722.95 |
Total FFY 2022 |
$25,480.73 |
$31,850.90 |
$33,715.31 |
Cost Estimates and Available Resources
Summary by Funding Category
Highway Projects Federal Fiscal Year 2023
Highway FFY 2023 |
Estimated Needs MVMPO (in 1000s) Federal Portion of Cost |
Estimated Needs MVMPO (in 1000s) Total Project Cost |
Available Resources MVMPO Projects (in 1000s) (From Region Target if not Statewide Category) |
Regional Target Congestion Mitigation/AQ Program (CMAQ) |
|
|
|
Regional Target Highway Safety Program (HSIP) |
|
|
|
Regional Target Surface Transportation Block Grant Program (STBG) |
$8,990.67 |
$11,238.34 |
$11,238.34 |
Regional Target Transportation Alternatives Program (TAP) |
|
|
|
Regional Target Subtotals |
$8,990.67 |
$11,238.34 |
$11,238.34 |
Statewide Intersection Improvements (HSIP) |
$1,337.74 |
$1,486.38 |
$1,486.38 |
Statewide Bicycle and Pedestrian (CMAQ) |
$9,191.79 |
$11,489.74 |
$11,489.74 |
|
|
|
|
Total FFY 2023 |
$19,520.20 |
$24,214.46 |
$24,214.46 |
Cost Estimates and Available Resources
Summary by Funding Category
Highway Projects Federal Fiscal Year 2024
Highway FFY 2024 |
Estimated Needs MVMPO (in 1000s) Federal Portion of Cost |
Estimated Needs MVMPO (in 1000s) Total Project Cost |
Available Resources MVMPO Projects (in 1000s) (From Region Target if not Statewide Category) |
Regional Target Surface Transportation Block Grant Program (STBG) |
$9,108.51 |
$11,385.64 |
$11,385.64 |
Regional Target Subtotals |
$9,108.51 |
$11,385.64 |
$11,385.64 |
Statewide Bicycle and Pedestrian (CMAQ) |
$7,941.25 |
$9,926.57 |
$9,926.57 |
Statewide (SW) Bridge On-System NHS (NHPP) |
$39,812.73 |
$49,765.91 |
$49,765.91 |
Total FFY 2024 |
$56,862.49 |
$71,078.12 |
$71,078.12 |
Cost Estimates and Available Resources
Summary by Funding Category
Highway Projects Federal Fiscal Year 2025
Highway FFY 2025 |
Estimated Needs MVMPO (in 1000s) Federal Portion of Cost |
Estimated Needs MVMPO (in 1000s) Total Project Cost |
Available Resources MVMPO Projects (in 1000s) (From Region Target if not Statewide Category) |
Regional Target Surface Transportation Block Grant Program (STBG) |
$8,895.87 |
$11,119.84 |
$11,119.84 |
Regional Target Subtotals |
$8,895.87 |
$11,119.84 |
$11,119.84 |
Statewide Bicycle and Pedestrian (CMAQ) |
$6,719.50 |
$8,399.38 |
$8,399.38 |
Statewide (SW) Bridge On-System NHS (NHPP) |
$38,832.00 |
$48,540.00 |
$48,540.00 |
Statewide Roadway Reconstruction SRTS (TAP) |
$1,289.42 |
$1,611.77 |
$1,611.77 |
Total FFY 2025 |
$55,736.79 |
$69,670.99 |
$69,670.99 |
Cost Estimates and Available Resources
Summary by Funding Category
Highway Projects Federal Fiscal Year 2026
Highway FFY 2026 |
Estimated Needs MVMPO (in 1000s) Federal Portion of Cost |
Estimated Needs MVMPO (in 1000s) Total Project Cost |
Available Resources MVMPO Projects (in 1000s) (From Region Target if not Statewide Category) |
Regional Target Surface Transportation Block Grant Program (STBG) |
$8,664.86 |
$10,831.08 |
$10,831.08 |
Regional Target Subtotals |
$8,664.86 |
$10,831.08 |
$10,831.08 |
Statewide (SW) Bridge On-System NHS (NHPP) |
$81,170.10 |
$101,462.62 |
$101,462.62 |
Statewide (SW) Bridge Off-System (STBG-BR-Off) |
$2,721.86 |
$3,402.33 |
$3,402.33 |
Total FFY 2026 |
$92,556.82 |
$115,696.03 |
$115,696.03 |
MVRTA Financial Status
The FAST Act requires that projects appearing in the TIP must have an identified source of funding that will allow them to be completed within the time period contemplated. Transit projects appearing in the FY 2022 to 2026 TIP meet this criterion.
The MVRTA is apportioned FTA Section 5307, 5337, and 5339 funds directly based on urbanized area population and the 20 agreed-upon funding splits between other public transit agencies that fall into the Urbanized Zone Area (UZA). The following tables depict the resulting financial plan for each of the five fiscal years.
Planning Justification for Transit Projects
The Merrimack Valley regions FFYs 2022 to 2026 TIP federal aid transit projects are to be carried out using Sections 5307 funding received by the MVRTA from the FTA with the exception of the provision of operating assistance, the planning justification for the Section 5307 projects are contained in the Merrimack Valley Regional Transit Authoritys Five-Year Capital Program for 2022 to 2026.
Merrimack Valley Metropolitan Planning Organization
FFYs 2022 to 2026 Transportation Improvement Program
(FTA related funding categories only)
Total Costs including Federal, State and Local*
Fiscal Year |
Federal Programmed Operating/Maintenance Costs* (inc. Match) |
Federal Programmed Capital and Other Costs* (inc. Match) |
Total Federal + Match Programmed* |
Total Federal + Match Estimated Available Funds* |
2022 |
$14.44 |
$0.10 |
$14.54 |
$14.54 |
2023 |
$11.97 |
$0.10 |
$12.07 |
$12.07 |
2024 |
$11.61 |
$0.10 |
$11.71 |
$11.71 |
2025 |
$7.04 |
$0.10 |
$7.14 |
$7.14 |
2026 |
$7.23 |
$0.10 |
$7.33 |
$7.33 |
* Millions of dollars
Cost Estimates and Available Resources
Summary by Funding Category
2022 Transit Projects
FTA Funding Program Summaries (Federal dollars only)
Merrimack Valley Regional Transit Authority FTA Funding Programs |
Estimated Authorization FFY 2022 |
Regional TIP FFY 2022 |
Balance FFY 2022 (Authorization 2022 minus Regional TIP 2022) |
Section 5307 Capital and Planning Formula |
$6,014,425 |
|
$6,014,425 |
Section 5307 Transit Enhancements |
|
|
|
Subtotal |
$6,014,425 |
|
$6,014,425 |
Section 5307 Capital and Planning Formula Carryover |
$13,607,530 |
$3,034,140 |
$10,573,390 |
Section 5307 Operating Carryover |
|
|
|
Section 5307 Transit Enhancements Carryover |
|
|
|
Subtotal |
$13,607,530 |
$3,034,140 |
$10,573,390 |
Section 5307 Total |
$19,621,955 |
$3,034,140 |
$16,581,815 |
CARES Act Funding |
$4,975,320 |
$4,975,320 |
|
Section 5309 Bus |
|
|
|
Section 5309 Fixed Guideway |
|
|
|
Section 5309 Total |
|
|
|
Section 5310 Elderly and Disabled |
|
|
|
Section 5310 Elderly and Disabled Carryover |
|
|
|
Federal Aid Total |
$24,597,275 |
$8,009,460 |
$16,587,815 |
Other Transit Funding (Non-Federal Aid) |
$40,735 |
$40,735 |
$0 |
Other Transit Funding (Non-Federal Aid) Transportation Development Credits (TDC) |
$317,785 |
$317,785 |
$0 |
Cost Estimates and Available Resources
Summary by Funding Category
2023 Transit Projects
FTA Funding Program Summaries (Federal dollars only)
Merrimack Valley Regional Transit Authority FTA Funding Programs |
Estimated Authorization FFY 2023 |
Regional TIP FFY 2023 |
Balance FFY 2023 (Authorization 2023 minus Regional TIP 2023) |
Section 5307 Capital and Planning Formula |
$6,074,570 |
$0 |
$6,074,570 |
Section 5307 Transit Enhancements |
|
|
|
Subtotal |
$6,074,570 |
$0 |
$6,074,570 |
Section 5307 Capital and Planning Formula Carryover |
$16,587,815 |
$5,567,720 |
$11,020,095 |
Section 5307 Operating Carryover |
|
|
|
Section 5307 Transit Enhancements Carryover |
|
|
|
Subtotal |
$16,587,815 |
$5,567,720 |
$11,020,095 |
Section 5307 Total |
$22,662,385 |
$5,567,720 |
$17,094,665 |
CARES Act Funding |
|
|
$0 |
Section 5309 Bus |
|
|
|
Section 5309 Fixed Guideway |
|
|
|
Section 5309 Total |
|
|
|
Section 5310 Elderly and Disabled |
|
|
|
Section 5310 Elderly and Disabled Carryover |
|
|
|
Section 5339 Bus and Bus Related Equipment and Facilities |
|
|
|
Federal Aid Total |
$22,662,385 |
$5,567,720 |
$17,094,665 |
Other Transit Funding (Non-Federal Aid) |
$876,880 |
$876,880 |
$0 |
Cost Estimates and Available Resources
Summary by Funding Category
2024 Transit Projects
FTA Funding Program Summaries (Federal dollars only)
Merrimack Valley Regional Transit Authority FTA Funding Programs |
Estimated Authorization FFY 2024 |
Regional TIP FFY 2024 |
Balance FFY 2024 (Authorization 2024 minus Regional TIP 2024) |
Section 5307 Capital and Planning Formula |
$6,135,315 |
$0 |
$6,135,315 |
Section 5307 Transit Enhancements |
|
|
|
Subtotal |
$6,135,315 |
$0 |
$6,135,315 |
Section 5307 Capital and Planning Formula Carryover |
$17,094,665 |
$7,526,735 |
$9,567,930 |
Section 5307 Operating Carryover |
|
|
|
Section 5307 Transit Enhancements Carryover |
|
|
|
Subtotal |
$17,094,665 |
$7,526,735 |
$9,567,930 |
Section 5307 Total |
$23,229,980 |
$7,526,735 |
$15,703,245 |
Section 5309 Bus |
|
|
|
Section 5309 Fixed Guideway |
|
|
|
Section 5309 Total |
|
|
|
Section 5310 Elderly and Disabled |
|
|
|
Section 5310 Elderly and Disabled Carryover |
|
|
|
Section 5339 Bus and Bus Related Equipment and Facilities |
|
|
|
Federal Aid Total |
$23,229,980 |
$7,526,735 |
$15,703,245 |
Other Transit Funding (Non-Federal Aid) |
$0 |
$0 |
$0 |
Cost Estimates and Available Resources
Summary by Funding Category
2025 Transit Projects
FTA Funding Program Summaries (Federal dollars only)
Merrimack Valley Regional Transit Authority FTA Funding Programs |
Estimated Authorization FFY 2025 |
Regional TIP FFY 2025 |
Balance FFY 2025 (Authorization 2025 minus Regional TIP 2025) |
Section 5307 Capital and Planning Formula |
$6,196,670 |
$0 |
$6,196,670 |
Section 5307 Transit Enhancements |
|
|
|
Subtotal |
$6,196,670 |
$0 |
$6,196,670 |
Section 5307 Capital and Planning Formula Carryover |
$15,703,245 |
$5,277,450 |
$10,425,795 |
Section 5307 Operating Carryover |
|
|
|
Section 5307 Transit Enhancements Carryover |
|
|
|
Subtotal |
$15,703,245 |
$5,277,450 |
$10,425,795 |
Section 5307 Total |
$21,899,915 |
$5,277,450 |
$16,622,465 |
Section 5309 Bus |
|
|
|
Section 5309 Fixed Guideway |
|
|
|
Section 5309 Total |
|
|
|
Section 5310 Elderly and Disabled |
|
|
|
Section 5310 Elderly and Disabled Carryover |
|
|
|
Section 5339 Bus and Bus Related Equipment and Facilities |
|
|
|
Federal Aid Total |
$21,899,915 |
$5,277,450 |
$16,622,465 |
Other Transit Funding (Non-Federal Aid) |
$0 |
$0 |
$0 |
Cost Estimates and Available Resources
Summary by Funding Category
2026 Transit Projects
FTA Funding Program Summaries (Federal dollars only)
Merrimack Valley Regional Transit Authority FTA Funding Programs |
Estimated Authorization FFY 2026 |
Regional TIP FFY 2026 |
Balance FFY 2026 (Authorization 2026 minus Regional TIP 2026) |
Section 5307 Capital and Planning Formula |
$6,258,640 |
$0 |
$6,258,640 |
Section 5307 Transit Enhancements |
|
|
|
Subtotal |
$6,258,640 |
$0 |
$6,258,640 |
Section 5307 Capital and Planning Formula Carryover |
$16,622,465 |
$5,433,375 |
$11,189,090 |
Section 5307 Operating Carryover |
|
|
|
Section 5307 Transit Enhancements Carryover |
|
|
|
Subtotal |
$16,622,465 |
$5,433,375 |
$11,189,090 |
Section 5307 Total |
$22,881,105 |
$5,433,375 |
$17,447,730 |
Section 5309 Bus |
|
|
|
Section 5309 Fixed Guideway |
|
|
|
Section 5309 Total |
|
|
|
Section 5310 Elderly and Disabled |
|
|
|
Section 5310 Elderly and Disabled Carryover |
|
|
|
Section 5339 Bus and Bus Related Equipment and Facilities |
|
|
|
Federal Aid Total |
$22,881,105 |
$5,433,375 |
$17,447,730 |
Other Transit Funding (Non-Federal Aid) |
$0 |
$0 |
$0 |
State Fiscal Year 2020 (Actual), 2021 (Adopted Budget), and 2022 to 2026 (Projected)
The numbers below represent actual numbers for the previous year, the current year budget/forecast approved by the MVRTA Advisory Board, and Projections for the out-years. These numbers indicate that there are sufficient revenues projected to meet the operating needs of the MVRTA.
|
Audit |
Adopted Budget |
DRAFT Budget #3 |
Projected |
Projected |
Projected |
Projected |
Operating Revenue |
Actual |
Rev #2 4/1/2021 |
4/1/2021 |
Yr Two |
Yr Three |
Yr Four |
Yr Five |
|
2020 |
2021 |
2022 |
2023 |
2024 |
2025 |
2026 |
Farebox |
$1,262,964 |
$634,765 |
$1,076,320 |
$1,714,880 |
$1,732,020 |
$1,749,335 |
$1,766,830 |
Section 5307 |
$5,000,807 |
|
|
$332,645 |
$5,079,945 |
$4,992,260 |
$5,154,730 |
Section 5311 |
|
|
|
|
|
|
|
CARES |
|
$5,033,995 |
$6,394,825 |
$4,833,635 |
|
|
|
CMAQ/TDM |
|
|
|
|
|
|
|
Fully Funded* |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MVRTA Transit Operations and Maintenance Summary Table
State Fiscal Year 2020 (Actual), 2021 (Adopted Budget), and 2022 to 2026 (Projected) (Continued)
|
Audit |
Adopted Budget |
Draft Budget #3 |
Projected |
Projected |
Projected |
Projected |
Operating Revenue |
Actual |
Rev #2 4/1/2021 |
4/1/2021 |
Yr Two |
Yr Three |
Yr Four |
Yr Five |
|
2020 |
2021 |
2022 |
2023 |
2024 |
2025 |
2026 |
Advertising |
$55,688 |
$23,885 |
$25,000 |
$44,620 |
$44,620 |
$44,620 |
$44,620 |
Interest Income |
$24,525 |
$1,000 |
$6,000 |
$24,700 |
$24,700 |
$24,700 |
$24,700 |
Rental Income |
|
|
|
|
|
|
|
State Contract Assistance** |
$7,253,008 |
$7,509,670 |
$7,697,410 |
$7,967,005 |
$8,206,020 |
$8,452,200 |
$8,705,765 |
Local Assessment |
$4,043,582 |
$4,372,625 |
$4,770,895 |
$5,229,030 |
$5,658,225 |
$6,107,610 |
$6,261,840 |
Other: (Define) |
$1,314,466 |
$953,640 |
$978,955 |
$1,216,320 |
$1,240,645 |
$1,253,050 |
$1,278,110 |
$18,955,040 |
$18,529,580 |
$20,949,405 |
$21,362,835 |
$21,986,175 |
$21,623,775 |
$23,236,595 |
MVRTA Transit Operations and Maintenance Summary
State Fiscal Year 2020 (Actual), 2021 (Adopted Budget), and 2022 to 2026 (Projected) (Continued)
Operating Expenses *** |
Actual |
Rev #2 4/1/2021 |
Draft #3 4/1/2021 |
Yr Two |
Yr Three |
Yr Four |
Yr Five |
|
2020 |
2021 |
2022 |
2023 |
2024 |
2025 |
2026 |
Total (See Below) |
$18,955,040 |
$18,529,580 |
$20,949,405 |
$21,362,835 |
$21,986,175 |
$21,623,775 |
$23,236,595 |
Footnotes:
* Fully funded refers to contract work often to Human Service Agencies
** Operating assistance provided by the State
*** Description of Operating Expenses: Salaries and Wages; Fringe Benefits: Legal, Accounting and Professional Services; Promotion/Marketing; Insurance; Equipment Leases and Rentals; Real Property Leases and Rentals; Non-capitalized Maintenance/Repair; Fuel costs; Tire costs; Office Supplies and Equipment; Interest expense; Utilities; Management Fees; Travel and Training; and Other miscellaneous expense items.
Regional Target Projects
Project ID |
Location |
Project Description |
Mass DOT District |
Funding Category |
Total Programmed Funds |
Project Status |
608298 |
Groveland |
Groveland-Groveland Community Trail |
4 |
STBG |
$1,984,861 |
100% Design. FY 2021. |
608761 |
Haverhill |
Haverhill-Intersection Reconstruction on Rt. 108 (Newton Road) at Rt. 110 (Kenoza Ave. and Amesbury Rd.) |
4 |
STBG |
$1,980,067 |
100% Design. FY 2021. |
609251 |
Lawrence |
Lawrence-Intersection Improvements at South Broadway (Route 28) and Mount Vernon Street |
4 |
STBG |
$1,218,368 |
Advertised 1/16/21. |
S10777 |
MVRTA |
MVRTA Flex to FTA to Replace Yr 2009 Buses with New Buses Delivery 2022 (7 of 9) |
4 |
Flex to FTA |
$3,467,361 |
Ordered-Delivery 2022 |
Part C. 3. Status on Implementation of FFY 2021 TIP Projects
Project Number |
Project Description |
Carry Over |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
Project Status |
RTD0008602
|
SGR Replace 1 model yr 2016 supervisory vehicle |
|
$38,320 |
$9,580 |
$0 |
$0 |
$0 |
$47,900 |
Ordered |
|
Replace Model Yr 2009 buses delivery 2022 (2 of 9) |
|
$495,337 |
$495,337 |
|
|
|
$990,674 |
Ordered, Delivery 2022 |
RTD0009132 |
SGR Replace Security Camera system at McGovern Center |
2020-$104,800 |
$104,800 |
$26,200 |
|
|
|
$131,000 |
RFP Responses under Review |
RTD0008595 |
OPERATING ASSISTANCE |
|
$558,120 |
$0 |
$558,120 |
$0 |
$0 |
$1,116,240 |
Ongoing |
RTD0008592 |
PREVENTIVE MAINTENANCE |
|
$2,796,775 |
$0 |
$699,195 |
$0 |
$0 |
$3,495,970 |
Ongoing |
RTD0008594 |
SHORT RANGE TRANSIT PLANNING |
|
$80,000 |
$0 |
$0 |
$0 |
$20,000 |
$100,000 |
Ongoing |
Part C. 3. Status on Implementation of FFY 2021 TIP Projects
FFY 2021 Transit Projects (Cont.)
Project Number |
Project Description |
Carry Over |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
Project Status |
RTD0009131 |
Riverbank stabilization Construction |
2020-$1,400,265 |
$1,400,265 |
$350,065 |
$0 |
$0 |
$0 |
$1,750,330 |
Moved to 2022 of 2022 to 2026 TIP |
RTD0008596 |
Replace 16 Model Yr 2015 vans with new Delivery 2021 |
|
$590,240 |
$590,240 |
$0 |
$0 |
$0 |
$1,180,480 |
Ordered, Delivery June 2021 |
RTD0008593 |
NON-FIXED ROUTE ADA PARA SERVICE |
|
$1,392,850 |
$0 |
$348,215 |
$0 |
$0 |
$1,741,065 |
Ongoing |
RTD0010047 |
SGR Replace 1 Model Yr 2016 Supervisory Vehicle |
|
$46,000 |
$0 |
$0 |
$11,500* |
$0 |
$46,000* |
Ordered |
RTD0010048 |
SGR Replace piping and related connections to underground gasoline tank |
|
$50,000 |
$0 |
$0 |
$12,500* |
$0 |
$50,000* |
Work scheduled for Jan 2021 weather permitting |
RTD0010049 |
Purchase of new bus and van tires to replace used tires |
|
$65,000 |
$0 |
$0 |
$16,250* |
$0 |
$65,000* |
Complete |
*TDC Transportation Development Credits are not included in Totals
Part C. 3. Status on Implementation of FFY 2021 TIP Projects
FFY 2021 Transit Projects (Cont.)
Project Number |
Project Description |
Carry Over |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
Project Status |
RTD0010050 |
Purchase licenses to upgrade diagnostic engine and transmission software |
|
$5,000 |
$0 |
$0 |
$1,250* |
$0 |
$5,000* |
Complete |
RTD0010051 |
SGR Replace HVAC Unit in Money Room |
|
$6,938 |
$0 |
$0 |
$1,735* |
$0 |
$6,938* |
Complete |
RTD0010305 |
Replace 2 servers/ related switches at MVRTA HQ |
|
$15,218 |
$3,804 |
|
|
|
$19,022 |
|
RTD0010306 |
Replace Security Surveillance system at Gateway Parking Area |
|
$117,871 |
$29,468 |
|
|
|
$147,339 |
|
RTD0010307 |
Replace Security Surveillance system at MVRTA Haverhill Intermodal Parking Facility |
|
$51,613 |
$12,903 |
|
|
|
$64,516 |
|
*TDC Transportation Development Credits are not included in Totals
Part C. 3. Status on Implementation of FFY 2021 TIP Projects
FFY 2021 Transit Projects (Cont.)
Project Number |
Project Description |
Carry Over |
Federal Funds |
RTACAP |
SCA |
TDC |
Local Funds |
Total |
Project Status |
RTD0010308 |
Purchase MDT units camera and communication equipment for 9 ADA service vehicles |
|
$63,034 |
$15,759 |
|
|
|
$78,793 |
|
RTD0010309 |
Upgrade security front gate entrance Control Pad at MVRTA HQ |
|
$2,000 |
$500 |
|
|
|
$2,500 |
|
RTD0010310 |
Install Cloud Based data storage system at MVRTA HQ |
|
$10,313 |
$2,578 |
|
|
|
$12,891 |
|
RTD0010311 |
Replace external security cameras on buses and vans |
|
$4,304 |
$1,076 |
|
|
|
$5,380 |
|
Air Quality Conformity Determination
Merrimack Valley Metropolitan Planning Organization (MVMPO)
FFY 2022 to 2026 Transportation Improvement Program
This section documents the latest air quality conformity determination for the 1997 ozone National Ambient Air Quality Standards (NAAQS) in the MVMPO Region. It covers the applicable conformity requirements according to the latest regulations, regional designation status, legal considerations, and federal guidance. Further details and background information are provided below:
Introduction
The 1990 Clean Air Act Amendments (CAAA) require metropolitan planning organizations within nonattainment and maintenance areas to perform air quality conformity determinations prior to the approval of Long-Range Transportation Plans (LRTPs) and Transportation Improvement Programs (TIPs), and at such other times as required by regulation. Clean Air Act (CAA) section 176(c) (42 U.S.C. 7506(c)) requires that federally funded or approved highway and transit activities are consistent with (conform to) the purpose of the State Implementation Plan (SIP). Conformity to the purpose of the SIP means that Federal Highway Administration (FHWA) and Federal Transit Administration (FTA) funding and approvals are given to highway and transit activities that will not cause or contribute to new air quality violations, worsen existing violations, or delay timely attainment of the relevant NAAQS or any interim milestones (42 U.S.C. 7506(c)(1)). EPAs transportation conformity rules establish the criteria and procedures for determining whether metropolitan transportation plans, transportation improvement programs (TIPs), and federally supported highway and transit projects conform to the SIP (40 CFR Parts 51.390 and 93).
A nonattainment area is one that the U.S. Environmental Protection Agency (EPA) has designated as not meeting certain air quality standards. A maintenance area is a nonattainment area that now meets the standards and has been re-designated as maintaining the standard. A conformity determination is a demonstration that plans, programs, and projects are consistent with the State Implementation Plan (SIP) for attaining the air quality standards. The CAAA requirement to perform a conformity determination ensures that federal approval and funding go to transportation activities that are consistent with air quality goals.
Legislative and Regulatory Background
The entire Commonwealth of Massachusetts was previously classified as nonattainment for ozone, and was divided into two nonattainment areas. The Eastern Massachusetts ozone nonattainment area included Barnstable, Bristol, Dukes, Essex, Middlesex, Nantucket, Norfolk, Plymouth, Suffolk, and Worcester counties. Berkshire, Franklin, Hampden, and Hampshire counties comprised the Western Massachusetts ozone nonattainment area. With these classifications, the 1990 Clean Air Act Amendments (CAAA) required the Commonwealth to reduce its emissions of volatile organic compounds (VOCs) and nitrogen oxides (NOx), the two major precursors to ozone formation to achieve attainment of the ozone standard.
The 1970 Clean Air Act defined a one-hour national ambient air quality standard (NAAQS) for ground-level ozone. The 1990 CAAA further classified degrees of nonattainment of the one-hour standard based on the severity of the monitored levels of the pollutant. The entire commonwealth of Massachusetts was classified as being in serious nonattainment for the one-hour ozone standard, with a required attainment date of 1999.The attainment date was later extended, first to 2003 and a second time to 2007.
In 1997, the EPA proposed a new, eight-hour ozone standard that replaced the one-hour standard, effective June 15, 2005. Scientific information had shown that ozone could affect human health at lower levels, and over longer exposure times than one hour. The new standard was challenged in court, and after a lengthy legal battle, the courts upheld it. It was finalized in June 2004.The eight-hour standard is 0.08 parts per million, averaged over eight hours and not to be exceeded more than once per year. Nonattainment areas were again further classified based on the severity of the eight-hour values. Massachusetts as a whole was classified as being in moderate nonattainment for the eight-hour standard, and was separated into two nonattainment areas, Eastern Massachusetts and Western Massachusetts.
In March 2008, EPA published revisions to the eight-hour ozone NAAQS establishing a level of 0.075 ppm, (March 27, 2008; 73 FR 16483). In 2009, EPA announced it would reconsider this standard because it fell outside of the range recommended by the Clean Air Scientific Advisory Committee. However, EPA did not take final action on the reconsideration so the standard would remain at 0.075 ppm.
After reviewing data from Massachusetts monitoring stations, EPA sent a letter on December 16, 2011 proposing that only Dukes County would be designated as nonattainment for the new proposed 0.075 ozone standard. Massachusetts concurred with these findings.
On May 21, 2012, (77 FR 30088), the final rule was published in the Federal Register, defining the 2008 NAAQS at 0.075 ppm, the standard that was promulgated in March 2008. A second rule published on May 21, 2012 (77 FR 30160), revoked the 1997 ozone NAAQS to occur one year after the July 20, 2012 effective date of the 2008 NAAQS.
Also on May 21, 2012, the air quality designations areas for the 2008 NAAQS were published in the Federal Register. In this Federal Register, the only area in Massachusetts that was designated as nonattainment is Dukes County. All other Massachusetts counties were designated as attainment/unclassified for the 2008 standard. On March 6, 2015, (80 FR 12264, effective April 6, 2015) EPA published the Final Rulemaking, Implementation of the 2008 National Ambient Air Quality Standards (NAAQS) for Ozone: State Implementation Plan Requirements; Final Rule. This rulemaking confirmed the removal of transportation conformity to the 1997 Ozone NAAQS and the replacement with the 2008 Ozone NAAQS, which (with actually a stricter level of allowable ozone concentration than the 1997 standards) classified Massachusetts as Attainment/unclassifiable (except for Dukes County).
However, on February 16, 2018, the United States Court of Appeals for the District of Columbia Circuit in South Coast Air Quality Mgmt. District v. EPA (South Coast II, 882 F.3d 1138) held that transportation conformity determinations must be made in areas that were either nonattainment or maintenance for the 1997 ozone NAAQS and attainment for the 2008 ozone NAAQS when the 1997 ozone NAAQS was revoked. These conformity determinations are required in these areas after February 16, 2019. On November 29, 2018, EPA issued Transportation Conformity Guidance for the South Coast II Court Decision (EPA-420-B-18-050, November 2018) that addresses how transportation conformity determinations can be made in areas. According to the guidance, both Eastern and Western Massachusetts, along with several other areas across the country, are now defined as orphan nonattainment areas � areas that were designated as nonattainment for the 1997 ozone NAAQS at the time of its revocation (80 FR 12264, March 6, 2015) and were designated attainment for the 2008 ozone NAAQS in EPAs original designations rule for this NAAQS (77 FR 30160, May 21, 2012).
Current Conformity Determination
After 2/16/19, as a result of the court ruling and the subsequent federal guidance, transportation conformity for the 1997 NAAQS, intended as an anti-backsliding measure, now applies to both of Massachusetts orphan areas. Therefore, a conformity determination was made for the 1997 ozone NAAQS on the 2020-2040 Regional Transportation Plans. This conformity determination was finalized in July 2019 following each MPOs previous endorsement of their regional transportation plan, and approved by the Massachusetts Divisions of FHWA and FTA on October 15, 2019. This conformity determination continues to be valid for the MVMPO FFY 2022 to 2026 Transportation Improvement Program, and Massachusetts FFY 2022 to 2026 STIP, as each is developed from the conforming 2020 to 2040 Regional Transportation Plans.
The transportation conformity regulation at 40 CFR 93.109 sets forth the criteria and procedures for determining conformity. The conformity criteria for TIPs and RTPs include: latest planning assumptions (93.110), latest emissions model (93.111), consultation (93.112), transportation control measures (93.113(b) and (c), and emissions budget and/or interim emissions (93.118 and/or 93.119).
For the 1997 ozone NAAQS areas, transportation conformity for TIPs and RTPs for the 1997 ozone NAAQS can be demonstrated without a regional emissions analysis, per 40 CFR 93.109(c). This provision states that the regional emissions analysis requirement applies one year after the effective date of EPAs nonattainment designation for a NAAQS and until the effective date of revocation of such NAAQS for an area. The 1997 ozone NAAQS revocation was effective on April 6, 2015, and the South Coast II court upheld the revocation. As no regional emission analysis is required for this conformity determination, there is no requirement to use the latest emissions model, or budget or interim emissions tests.
Therefore, transportation conformity for the 1997 ozone NAAQS for the MVMPO FFYs 2022 to 2026 Transportation Improvement Program and 2020 to 2040 Regional Transportation Plans can be demonstrated by showing that remaining requirements in Table 1 in 40 CFR 93.109 have been met. These requirements, which are laid out in Section 2.4 of EPAs guidance and addressed below, include:
Latest planning assumptions (93.110)
� Consultation (93.112)
� Transportation Control Measures (93.113)
� Fiscal Constraint (93.108)
Latest Planning Assumptions:
The use of latest planning assumptions in 40 CFR 93.110 of the conformity rule generally apply to regional emissions analysis. In the 1997 ozone NAAQS areas, the use of latest planning assumptions requirement applies to assumptions about transportation control measures (TCMs) in an approved SIP (See following section on Timely Implementation of TCMs).
Consultation:
The consultation requirements in 40 CFR 93.112 were addressed both for interagency consultation and public consultation. Interagency consultation was conducted with FHWA, FTA, US EPA Region 1, MassDEP, and the Massachusetts MPOs on March 6, 2019 to discuss the latest conformity-related court rulings and resulting federal guidance. Regular and recurring interagency consultations have been held since on an (at least) annual schedule, with the most recent conformity consultation held on January 21, 2021. This ongoing consultation is conducted in accordance with the following:
� Massachusetts Air Pollution Control Regulations 310 CMR 60.03 Conformity to the State Implementation Plan of Transportation Plans, Programs, and Projects Developed, Funded or Approved Under Title 23 USC or the Federal Transit Act
� The Commonwealth of Massachusetts Memorandum of Understanding among the Massachusetts Department of Transportation, Massachusetts Department of Environmental Protection, Massachusetts Metropolitan Planning Organizations, and Regional Transit Authorities, titled The Conduct of Air Quality Planning and Coordination for Transportation Conformity (dated September 16, 2019)
Public consultation was conducted consistent with planning rule requirements in 23 CFR 450.
Title 23 CFR Section 450.324 and 310 CMR 60.03(6)(h) requires that the development of the TIP, Regional Transportation Plan (RTP), Unified Planning Work Program (UPWP) and Public Participation Plan (PPP) related certification documents provide an adequate opportunity for public review and comment. Section 450.316(b) also establishes the outline for MPO public participation programs. The Merrimack Valley MPOs Public Participation Plan was formally adopted in 2017 and can be found on the MVPC website at https://mvpc.org/wp-content/uploads/MVMPO-final-PPP-as-Amended-through-March-2017-1.pdf. The Public Participation Plan ensures that the public will have access to the TIP/RTP/UPWP and PPP and all supporting documentation, provides for public notification of the availability of the Draft TIP/RTP/UPWP and PPP documents as well as Draft Amendments to these documents and the publics right to review the documents and comment thereon, and provides a 21-day public review and comment period prior to the adoption of the TIP/RTP and UPWP and a 45-day public review and comment period for the PPP and related certification documents.
The public comment period for this conformity determination commenced on May 5, 2021. During the 21-day public comment period, any comments received were incorporated into this Plan. This allowed ample opportunity for public comment and MPO review of the draft document. The public comment period will close on May 25, 2021 and subsequently, the Merrimack Valley MPO is expected to endorse this air quality conformity determination before May 31, 2021. These procedures comply with the associated federal requirements.
Timely Implementation of Transportation Control Measures:
Transportation Control Measures (TCMs) have been required in the SIP in revisions submitted to EPA in 1979 and 1982. All SIP TCMs have been accomplished through construction or through implementation of ongoing programs. All of the projects have been included in the Regions Transportation Plan (present or past) as recommended projects or projects requiring further study.
Fiscal Constraint:
Transportation conformity requirements in 40 CFR 93.108 state that TIPs and transportation plans and must be fiscally constrained consistent with DOTs metropolitan planning regulations at 23 CFR part 450. The MVMPO 2022 to 2026 Transportation Improvement Program and 2020 to 2040 Regional Transportation Plan are fiscally constrained, as demonstrated in this document.
In summary and based upon the entire process described above, the Merrimack Valley MPO has prepared this conformity determination for the 1997 Ozone NAAQS in accordance with EPAs and Massachusetts latest conformity regulations and guidance. This conformity determination process demonstrates that the FFY 2022 to 2026 Transportation Improvement Program and the 2020-2040 Regional Transportation Plan meet the Clean Air Act and Transportation Conformity Rule requirements for the 1997 Ozone NAAQS, and have been prepared following all the guidelines and requirements of these rules during this time period.
Therefore, the implementation of the Merrimack Valley MPOs FFY 2022 to 2026 Transportation Improvement Program and the 2020 to 2040 Regional Transportation Plan are consistent with the air quality goals of, and in conformity with, the Massachusetts State Implementation Plan.
Projects Required for Implementation of ADA
Another requirement of 23 CFR 450.324 is that projects required for the implementation of the Americans with Disabilities Act (ADA) should be so marked. There are no projects in this TIP listing that are required for the implementation of the Americans with Disabilities Act and therefore no projects are marked as such. There are projects to replace existing accessible transit vehicles with new accessible transit vehicles, but these are replacements not implementations.
The Merrimack Valley Planning Commission (MVPC) operates its programs, services and activities in compliance with federal nondiscrimination laws including Title VI of the Civil Rights Act of 1964 (Title VI), the Civil Rights Restoration Act of 1987, and related statutes and regulations. Title VI prohibits discrimination in federally assisted programs and requires that no person in the United States of America shall, on the grounds of race, color or national origin (including limited English proficiency) be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity receiving federal assistance. Related federal nondiscrimination laws administrated by the Federal Highway Administration, the Federal Transit Administration, or both, prohibit discrimination on the basis of age, sex and disability. These protected categories are contemplated within MVPCs Title VI Program consistent with federal interpretation and administration. Additionally, MVPC provides meaningful access to its programs, services, and activities to individuals with limited English proficiency, in compliance with U.S. Department of Transportation policy and guidance on federal Executive Order 13166.
MVPC also complies with the Massachusetts Public Accommodation Law, M.G.L. Chapter 272, Sections 92a, 98, and 98a prohibiting making any distinction, discrimination, or restriction in admission to or treatment in a place of public accommodation based upon race, color, religious creed, national origin, sex, sexual orientation, disability, or ancestry. Likewise, MVPC complies with the Governors Executive Order 526, Section 4 requiring that all of its programs, activities, and services provided, performed, licensed, chartered, funded, regulated, or contracted for shall be conducted without unlawful discrimination based upon race, color, age, gender, ethnicity, sexual orientation, gender identity or expression, religion, creed, ancestry, national origin, disability, veterans status (including Vietnam-era veterans), or background.
Additional Information
To request additional information regarding Title VI and related federal and state nondiscrimination obligations, please contact:
Title VI Program Coordinator
Merrimack Valley Metropolitan Planning Organization
c/o Merrimack Valley Planning Commission
160 Main Street
Haverhill, MA 01830-5061
(978) 374-0519, extension 15
Complaint Filing
To file a complaint alleging a violation of Title VI or related federal nondiscrimination law, contact the Title VI Program Coordinator (above) within one hundred and eighty (180) days of the alleged discriminatory conduct.
To file a complaint alleging a violation of the Commonwealths Public Accommodation Law, contact the Massachusetts Commission Against Discrimination within three hundred (300) days of the alleged discriminatory conduct at:
Massachusetts Commission Against Discrimination (MCAD)
One Ashburton Place, 6th Floor
Boston, MA 02109
(617) 994-6000
TTY: (617) 994-6196
Environmental Justice from a transportation perspective is the fair treatment and meaningful involvement of all people regardless of race, color, national origin, or income with respect to the development, implementation, and enforcement of transportation laws, regulations, and policies.
Each Federal agency shall make achieving environmental justice part of its mission by identifying and addressing, as appropriate, disproportionately high and adverse human health or environmental effects of its programs, policies, and activities on minority populations and low-income populations.
MVMPO Merrimack Valley Transportation Committee Equity Working Group
The MVMPO Merrimack Valley Transportation Committees (MVTC) purpose is to advise the MVMPO and participate in the MVMPO regions federally certified transportation planning process. Its membership provides for the involvement of local government officials, transportation professionals, transportation providers, and individuals experienced in economic development, freight, commuter rail, smart growth, environmental issues, regional planning, and other interest groups, ensuring broad representation and a geographical balance of its participants.
MVTC Equity Working Group
The MVMPO is responsible for promoting, securing and evaluating public involvement in its transportation planning process. In particular, it is responsible for identifying and seeking meaningful participation of the regions minority and low-income (Environmental Justice) populations and in working to reduce participation barriers for such populations.
The MVMPOs established EJ process includes identification of Census-based statistical areas within its region where:
a) the percentage of minority populations exceeds the average percentage of minority population for the region as a whole;
b) household incomes are 65% or less of area median income (AMI), and
c) there are concentrations of households with limited English proficiency (LEP).
The MVMPO established an Equity Working Group to provide the MVMPO members and staff with the perspectives of individuals and organizations representing low-income and minority populations. It is also an opportunity for MVMPO staff and EJ stakeholders to exchange information, evaluate policies, plans and projects, and generate ideas for future projects. The MVMPO staff regularly consults with members of the Equity Working Group.
To help inform the work of the MVMPO, it is helpful to have members of the Equity Working Group who have individual and/or collective knowledge and expertise in working with EJ populations on:
a) Disabilities
b) Education
c) English proficiency
d) Elder Affairs
e) Faith-based community service
f) Minority advocacy
g) Neighborhood organization
h) Non-profit community development
i) Public Health
j) Veterans Affairs
k) Workforce training and development
The following tables illustrate a geographic and social equity analysis of highway funding in the Merrimack Valley MPO region. Haverhill, Lawrence and Methuen are designated as Title VI and Environmental Justice (EJ) communities. The Title VI communities have tracts with higher than average percentage of minorities than the regional average percentage and the same three communities are EJ communities with lower than average median income in some census tracts.
The following table shows the percent of population in Title VI / EJ communities relative to the percent of Federal highway funding programmed in the 2022 to 2026 TIP.
|
Region Population (ACS 11 to 15) |
Percent of Total Population |
TIP Project Investment |
Percent of Projects by Total Investment |
Within Title VI / EJ community |
189,490 |
55% |
$185,601,751 |
59% |
Outside Title VI / EJ community |
154,420 |
45% |
$126,908,737 |
41% |
Total |
343,910 |
100% |
$312,510,488 |
100% |
This table illustrates consistency between the percent of population in Title VI/ EJ areas and the percent of funding in those areas.
Persons with Limited English Proficiency (LEP) are those who self-report on the Census as speaking English less than very well. USDOT guidance defines Safe harbor languages as those non-English languages that are spoken by LEP persons who make up at least 5% of the population, or 1,000 individuals, whichever is less. Using this definition for LEP people ages 5+ living in the region the number of LEP individuals exceeds the 1,000-person threshold in Spanish (32,513 people) and Chinese (1,124 people). The LEP persons in these two languages represent 83% of all LEP people in the region. Communities with more than 1,000 individuals whose Safe-harbor language is Spanish are Haverhill (3,010 people), Lawrence (25,355 people) and Methuen (3,352 people). Andover has the highest number of individuals (630 people) whose Safe-harbor language is Chinese. Therefore these 4 communities are considered LEP communities.
The following table shows the percent of population age 5+ in LEP communities relative to the percent of Federal highway funding programmed in the 2022 to 2026 TIP.
|
Region Population Age 5+ (ACS 11 to 15) |
Percent of Total Population Age 5+ (ACS 11 to 15) |
TIP Project Investment |
Percent of Projects by Total Investment |
Within LEP community |
208,754 |
65% |
249,826,889 |
80% |
Outside LEP community |
112,973 |
35% |
62,683,599 |
21% |
Total |
321,727 |
100% |
$312,510,488 |
100% |
This table illustrates consistency between the percent of population in LEP areas and the percent of funding in those areas.
All of the Federal transit funding (100%) is considered to benefit Title VI, EJ and LEP communities because all of the MVRTA fixed routes originate in the Title VI / EJ / LEP communities of Haverhill or Lawrence, or provide connections to these routes. The paratransit service also provides access to and from the Title VI, EJ and LEP communities.
All but one of the MVMPO region communities have had, or are programmed to have, Federally funded projects from 2017 to 2026. (Looking at the tables that follow West Newbury, which is not a Title VI / EJ or LEP community, does not have a federally funded project in the ten-year period, however it did have a Federally funded project in 2015.
The tables on the following pages show the projects included in the analysis for FFYs 2022 to 2026 and a summary chart showing the number of projects and the funding by community, and whether the community is a Title VI (high percentage of minorities), an EJ (high percentage of low-income households) and/or LEP community. This is followed by a table and analysis chart for projects programmed in FFYs 2017 to 2021.
For Title VI and EJ communities, the results show that for FFYs 2022 to 2026, 56% of the total number of projects are in Title VI and EJ communities. Considering the data for percent of funding, 59% of the funding is in Title VI and EJ communities.
For LEP communities, the results show that for FFYs 2022 to 2026, 60% of the total number of projects are in LEP communities. Considering the data for percent of funding, 80% of the funding is in LEP communities.
For Title VI and EJ communities, the results show that for FFYs 2017 to 2021, 56% of the total number of projects are in Title VI communities and EJ communities. Considering the data for percent of funding, 68% of the funding is in Title VI communities and EJ communities.
For LEP communities, the results show that for FFYs 2017 to 2021, 59% of the total number of projects are in LEP communities. Considering the data for percent of funding, 73% of the funding is in LEP communities.
All of the Transit funding (100%) is considered to benefit Title VI, EJ and LEP communities because all of the MVRTA fixed routes originate in Haverhill, or in Lawrence, or provide connections to these routes. The paratransit service also provides access to and from the Title VI and EJ communities. There are two mappable transit projects in the FFYs 2022 to 2026 TIP. The Riverbank Stabilization Project Construction is labeled MVRTA�1 and the MVRTA Headquarters (HQ) Facility Repairs is labeled MVRTA�2. There is only one mappable transit project in the FFYs 2017 to 2021 project list, the Design of the Riverbank Stabilization project, it is labelled on the relevant maps as RTD-7127. The transit project maps also include the fixed-route bus service routes.
Equity Analysis Maps
MVMPO: FFYs 2022 to 2026 TIP Projects by Community
MVMPO: FFYs 2017 to 2021 Projects by Community
FFYs 2022 to 2026 MVMPO Statewide and Regional Target Highway Funding
Projects by Community for Equity Analysis
Community |
Project Number |
Project Description |
Total Funding Programmed |
FFY |
Title VI Community |
EJ Community |
LEP Community |
Andover |
606522 |
Andover Bridge Rehab., I-495 over Rt. 28 and RR |
$64,225,138 |
2024to 2026 |
No |
No |
Yes |
Georgetown/ Boxford |
607541 |
Georgetown/ Boxford Border to Boston Trail |
$2,714,316 |
2025 |
No |
No |
No |
Georgetown/ Newbury |
607542 |
Georgetown/ Newbury Border to Boston Trail |
$5,685,060 |
2025 |
No |
No |
No |
Haverhill |
605306 |
Haverhill Bridge Replacement I-495 over Merrimack (H-12-039) |
$12,994,233 |
2022 |
Yes |
Yes |
Yes |
Haverhill |
609466 |
Haverhill Bridge Replacement I-495 over Merrimack (H-12-040) |
$78,161,628 |
2024 to 2026 |
Yes |
Yes |
Yes |
Haverhill |
605304 |
Haverhill-Bridge Replacement Bridge St (Rt 125) over Merrimack and B&M RR |
$57,381,766 |
2024 to 2026 |
Yes |
Yes |
Yes |
FFYs 2022 to 2026 MVMPO Statewide and Regional Target Highway Funding
Projects by Community for Equity Analysis (Cont.)
Community |
Project Number |
Project Description |
Total Funding Programmed |
FFY |
Title VI Community |
EJ Community |
LEP Community |
Lawrence |
609509 |
Lawrence Intersection Improvements at Merrimack Street and South Broadway (Route 28) |
$1,502,354 |
2022 |
Yes |
Yes |
Yes |
Lawrence |
610923 |
Lawrence Intersection Reconstruction at Marston Street and East Haverhill Street |
$1,658,011 |
2022 |
Yes |
Yes |
Yes |
Lawrence |
608930 |
Lawrence Lawrence Manchester Rail Corridor (LMRC) Rail Trail |
$21,416,304 |
2023 to 2024 |
Yes |
Yes |
Yes |
Lawrence |
612002 |
Lawrence Community Day Arlington Improvements (SRTS) |
$1,611,774 |
2025 |
Yes |
Yes |
Yes |
Lawrence |
612074 |
Lawrence Bridge Replacement, L-04-012, Short Street over Spicket River |
$3,402,326 |
2026 |
Yes |
Yes |
Yes |
Methuen |
610658 |
Methuen Intersection Improvements at Riverside Drive and Burnham Road |
$967,200 |
2023 |
Yes |
Yes |
Yes |
FFYs 2022 to 2026 MVMPO Statewide and Regional Target Highway Funding
Projects by Community for Equity Analysis (Cont.)
Community |
Project Number |
Project Description |
Total Funding Programmed |
FFY |
Title VI Community |
EJ Community |
LEP Community |
Newbury/ Newburyport/ Salisbury |
608494 |
Newbury/ Newburyport/ Salisbury Resurfacing Route 1 |
$9,722,950 |
2022 |
No |
No |
No |
North Andover |
608095 |
North Andover Corridor Rt.114 from Andover St. to Stop & Shop |
$25,392,871 |
2024 to 2026 |
No |
No |
No |
Rowley |
609392 |
Rowley Safety Improvements at Route 1, Central and Glen Streets |
$1,486,378 |
2023 |
No |
No |
No |
Salisbury |
602202 |
Salisbury Reconstruction of Route 1 (Lafayette Rd) |
$18,214,824 |
2023 to 2024 |
No |
No |
No |
MVRTA |
S12107 |
MVRTA Flex to FTA to Replace Yr 2011 Buses with New Clean Diesel Buses Order 1/2022 Delivery 6/2023 (6 of 8) |
$2,983,200 |
2022 |
Yes |
Yes |
Yes |
MVRTA |
S12108 |
MVRTA Flex to FTA to Replace Yr 2011 Buses with New Hybrid Buses Order 1/2022 Delivery 6/2023 (2 of 8) |
$1,401,200 |
2022 |
Yes |
Yes |
Yes |
FFYs 2022 to 2026 MVMPO Statewide and Regional Target Highway Funding
Projects by Community for Equity Analysis (Cont.)
Community |
Project Number |
Project Description |
Total Funding Programmed |
FFY |
Title VI Community |
EJ Community |
LEP Community |
MVRTA |
S12109 |
MVRTA Flex to FTA to Repower five (5) 2015 Transit Buses |
$314,185 |
2022 |
Yes |
Yes |
Yes |
MVRTA |
S12110 |
MVRTA Flex to FTA to Repower five (5) 2016 Transit Buses |
$328,560 |
2022 |
Yes |
Yes |
Yes |
MVRTA |
S12111 |
MVRTA Flex to FTA to Upgrade CAD/AVL and Automated Vehicle Announcement (AVA) |
$946,210 |
2022 |
Yes |
Yes |
Yes |
|
Total |
Projects 22 to 26 |
$312,510,488 |
|
|
|
|
FFYs 2022 to 2026 MVMPO Equity Analysis Highway Funding
Community |
Number of Projects |
Percent Of Projects |
TIP Funding |
Percent of Funding |
Title VI Community |
EJ Community |
LEP Community |
|
|
|
|
|
|
|
|
Amesbury |
0 |
0% |
$0 |
0% |
No |
No |
No |
Andover |
1 |
4% |
$64,225,138 |
20.6% |
No |
No |
Yes |
Boxford |
1 |
4% |
$1,357,158 |
0.4% |
No |
No |
No |
Georgetown |
2 |
8% |
$4,199,688 |
1.3% |
No |
No |
No |
Groveland |
0 |
0% |
$0 |
0% |
No |
No |
No |
Haverhill |
3 |
12% |
$148,537,627 |
47.5% |
Yes |
Yes |
Yes |
Lawrence |
5 |
20% |
$29,590,769 |
9.5% |
Yes |
Yes |
Yes |
Merrimac |
0 |
0% |
$0 |
0% |
No |
No |
No |
Methuen |
1 |
4% |
$967,200 |
0.3% |
Yes |
Yes |
Yes |
Newbury |
2 |
8% |
$6,083,513 |
1.9% |
No |
No |
No |
Newburyport |
1 |
4% |
$3,240,983 |
1.0% |
No |
No |
No |
North Andover |
1 |
4% |
$25,392,871 |
8.1% |
No |
No |
No |
Rowley |
1 |
4% |
$1,486,378 |
0.5% |
No |
No |
No |
Salisbury |
2 |
8% |
$21,455,807 |
6.9% |
No |
No |
No |
West Newbury |
0 |
0% |
$0 |
0% |
No |
No |
No |
MVRTA |
5 |
20% |
$5,973,355 |
1.9% |
Yes |
Yes |
Yes |
|
|
|
|
|
|
|
|
Total |
25 |
|
$312,510,488 |
|
|
|
|
Percent of Projects in Title VI Community = 56%
Percent of Projects in EJ Community = 56%
Percent of Projects in LEP Community = 60%
Percent of Funding in Title VI Community = 59%
Percent of Funding in EJ Community = 59%
Percent of Funding in LEP Community = 80%
FFYs 2017 to 2021 MVMPO Statewide and Regional Target Highway Funding
Projects by Community for Equity Analysis
Community |
Project Number |
Project Description |
Total Funding Programmed |
FFY |
Title VI Community |
EJ Community |
LEP Community |
Amesbury |
602418 |
Amesbury Elm St. Reconstruction (2019 = $3,955,071, 2020 = $7,223,053) |
$11,178,124 |
2019-2020 |
No |
No |
No |
Amesbury |
606669 |
Amesbury Powwow Riverwalk |
$671,207 |
2017 |
No |
No |
Yes |
Amesbury/ Salisbury |
607737 |
Amesbury/ Salisbury Trail Connector at I-95 |
$3,167,723 |
2018 |
No |
No |
No |
Andover/ Methuen |
607561 |
Andover/ Methuen IM I-93 |
$13,932,707 |
2017 |
No/ Yes |
No/ Yes |
Yes/ Yes |
Groveland |
608298 |
Groveland Community Trail from Main Street to King Street |
$1,984,861 |
2021 |
No |
No |
No |
Haverhill |
608027 |
Haverhill-Bradford Rail Trail Ext. |
$1,766,108 |
2020 |
Yes |
Yes |
Yes |
Haverhill |
608761 |
Haverhill Rt. 108 (Newton Road) at Rt. 110 (Kenoza Ave. and Amesbury Rd.) |
$1,980,067 |
2021 |
Yes |
Yes |
Yes |
Haverhill |
607573 |
Haverhill Route 97 (Broadway) |
$6,526,912 |
2017 |
Yes |
Yes |
Yes |
FFYs 2017 to 2021 MVMPO Statewide and Regional Target Highway Funding
Projects by Community for Equity Analysis (Cont.)
Community |
Project Number |
Project Description |
Total Funding Programmed |
FFY |
Title VI Community |
EJ Community |
LEP Community |
Haverhill |
605306 |
Haverhill Bridge Replacement I-495 over Merrimack (2018 = $19,797,733, 2019 = $23,703,426, 2020 = $15,305,880, 2021 = $0 (used obligation authority in Aug 2020 instead) |
$58,807,039 |
2018 to 2021 |
Yes |
Yes |
Yes |
Haverhill/ Merrimac/ Amesbury |
608187 |
Guide Signs on I-495 |
$4,451,342 |
2017 |
Yes/ No |
Yes/ No |
Yes/ No |
Lawrence |
608946 |
Lawrence Haverhill St (Route 110) at Ames Street |
$1,267,500 |
2018 |
Yes |
Yes |
Yes |
Lawrence |
608261 |
Lawrence Marston St./ Ferry St./ Commonwealth Ave. |
$1,350,694 |
2017 |
Yes |
Yes |
Yes |
Lawrence |
608002 |
Lawrence Safe Routes to School Bruce Elementary |
$2,016,148 |
2017 |
Yes |
Yes |
Yes |
FFYs 2017 to 2021 MVMPO Statewide and Regional Target Highway Funding
Projects by Community for Equity Analysis (Cont.)
Community |
Project Number |
Project Description |
Total Funding Programmed |
FFY |
Title VI Community |
EJ Community |
LEP Community |
Lawrence |
609251 |
Lawrence Intersection Improvements at South Broadway (Route 28) and Mount Vernon Street |
$1,218,368 |
2021 |
Yes |
Yes |
Yes |
Lawrence/ North Andover |
608809 |
Lawrence North Andover-Resurfacing Route 114 |
$2,123,453 |
2018 |
Yes/ No |
Yes/ No |
Yes/ No |
Newburyport |
608792 |
Newburyport SRTS |
$1,866,615 |
2019 |
No |
No |
No |
North Andover |
606159 |
North Andover Rt 125/ Mass Ave |
$5,446,662 |
2019 |
No |
No |
No |
MVRTA |
604585 |
Flex to FTA for MVRTA Cleaner Fuel Buses |
$645,840 |
2017 |
Yes |
Yes |
Yes |
MVRTA |
MV0001 |
Flex to FTA for MVRTA Cleaner Fuel Buses |
$698,541 |
2019 |
Yes |
Yes |
Yes |
MVRTA |
MV0003 |
Flex to FTA for MVRTA Bike Racks for Buses and for Transportation Centers |
$110,000 |
2019 |
Yes |
Yes |
Yes |
FFYs 2017 to 2021 MVMPO Statewide and Regional Target Highway Funding
Projects by Community for Equity Analysis (Cont.)
Community |
Project Number |
Project Description |
Total Funding Programmed |
FFY |
Title VI Community |
EJ Community |
LEP Community |
MVRTA |
S10777 |
MVRTA Flex to FTA to Replace Yr 2009 Buses with New Buses Delivery 2022 (7 of 9) |
$3,467,361 |
2021 |
Yes |
Yes |
Yes |
Salisbury |
605020 |
Salisbury Multi-use trail extension (Borders-to-Boston), includes new bridge S-02-004 |
$7,184,196 |
2018 |
No |
No |
No |
|
|
Total All Projects 2017 to 2021 |
$131,861,468 |
|
|
|
|
FFYs 2017 to 2021 MVMPO Equity Analysis Highway Funding
Community |
Number of Projects |
Percent Of Projects |
TIP Funding |
Percent of Funding |
Title VI Community |
EJ Community |
LEP Community |
|
|
|
|
|
|
|
|
Amesbury |
4 |
15% |
$14,916,973 |
11% |
No |
No |
No |
Andover |
1 |
4% |
$6,966,354 |
5% |
No |
No |
Yes |
Boxford |
0 |
0% |
$0 |
0% |
No |
No |
No |
Georgetown |
0 |
0% |
$0 |
0% |
No |
No |
No |
Groveland |
1 |
4% |
$1,984,861 |
2% |
No |
No |
No |
Haverhill |
5 |
19% |
$70,563,907 |
54% |
Yes |
Yes |
Yes |
Lawrence |
5 |
19% |
$6,914,437 |
5% |
Yes |
Yes |
Yes |
Merrimac |
1 |
4% |
$1,483,781 |
1% |
No |
No |
No |
Methuen |
1 |
4% |
$6,966,354 |
5% |
Yes |
Yes |
Yes |
Newbury |
0 |
0% |
$0 |
0% |
No |
No |
No |
Newburyport |
1 |
4% |
$1,866,615 |
1% |
No |
No |
No |
North Andover |
2 |
7% |
$6,508,389 |
5% |
No |
No |
No |
Rowley |
0 |
0% |
$0 |
0% |
No |
No |
No |
Salisbury |
2 |
7% |
$8,768,058 |
7% |
No |
No |
No |
West Newbury |
0 |
0% |
$0 |
0% |
No |
No |
No |
MVRTA |
4 |
15% |
$4,921,742 |
4% |
|
|
|
|
|
|
|
|
|
|
|
Total |
28 |
|
$131,861,468 |
|
|
|
|
Percent of Projects in Title VI Community = 56%
Percent of Projects in EJ Community = 56%
Percent of Projects in LEP Community = 59%
Percent of Funding in Title VI Community = 68%
Percent of Funding in EJ Community = 68%
Percent of Funding in LEP Community = 73%
FFYs 2022 to 2026 MVMPO Transit Projects Funding
FFY Year |
Project Number |
Project Description |
Total Project Cost |
2022 |
RTD0009669 |
Preventative Maintenance |
$3,611,335 |
2022 |
RTD0009671 |
Short Range Transit Planning |
$100,000 |
2022 |
RTD0009672 |
Operating Assistance |
$1,289,890 |
2022 |
RTD0009670 |
ADA Paratransit Service |
$1,801,630 |
2022 |
RTD0009673 |
Replace 9 Model Yr 2009 35 ft. buses delivery 2022 |
$4,458,030 |
2022 |
RTD0010053 |
MVRTA HQ Facility Repairs |
$682,000 |
2022 |
RTD0009680 |
Replace 1 Model Yr 2016 supervisory vehicle |
$48,870 |
2022 |
RTD0010107 |
Riverbank Stabilization Construction |
$2,546,000 |
2023 |
RTD0009674 |
Preventative Maintenance |
$3,730,510 |
2023 |
RTD0009675 |
Operating Assistance |
$1,478,730 |
2023 |
RTD0009676 |
ADA Paratransit Service |
$1,861,090 |
2023 |
RTD0009677 |
Replace 8 Model Yr 2011 35 ft. buses delivery 2023 |
$4,384,400 |
2023 |
RTD0009678 |
Replace 6 Model Yr 2017 Type E-2 vans delivery 2023 (RTD0009678) |
$469,620 |
2023 |
RTD0009679 |
Short Range Transit Planning |
$100,000 |
2023 |
RTD0009687 |
SGR Replace 1 Model Yr 2017 supervisory vehicle |
$50,335 |
2024 |
RTD0009688 |
Replace 1 model yr 2018 Supervisory Vehicle (RTD0009688) |
$51,845 |
FFYs 2022 to 2026 MVMPO Transit Projects Funding (Cont.)
FFY Year |
Project Number |
Project Description |
Total Project Cost |
2024 |
RTD0009681 |
Replace 8 model yr 2012 buses delivery 2024 (8 of 8) (RTD0009681) |
$4,703,200 |
2024 |
RTD0009682 |
Preventative Maintenance for Service |
$3,618,265 |
2024 |
RTD0009683 |
Operating Assistance for Service |
$1,429,680 |
2024 |
RTD0009684 |
ADA Paratransit Service |
$1,805,255 |
2024 |
RTD0009685 |
Short Range Transit Planning |
$100,000 |
2025 |
RTD0009689 |
Short Range Transit Planning (RTD0009689) |
$100,000 |
2025 |
RTD0009690 |
Preventative Maintenance for Service |
$3,690,630 |
2025 |
RTD0009691 |
Operating Assistance for Service |
$1,458,270 |
2025 |
RTD0009692 |
ADA Paratransit Service |
$1,841,365 |
2025 |
RTD00009693 |
Replace 1 Model Year 2019 Supervisory Vehicle |
$53,400 |
2026 |
RTD0010055 |
Preventative Maintenance for Service |
$3,810,350 |
2026 |
RTD0010057 |
ADA Paratransit Service |
$1,866,605 |
2026 |
RTD0010058 |
Short Range Transit Planning |
$100,000 |
2026 |
RTD0010059 |
Operating Assistance for Service |
$1,502,020 |
2026 |
RTD00010060 |
Replace 1 Model Year 2020 Supervisory Vehicle |
$55,000 |
|
|
Total Transit Project Funding 2022 to 2026 |
$52,798,325 |
FFYs 2017 to 2021 MVMPO Transit Projects Funding
FFY Year |
Project Number |
Project Description |
Total Project Cost |
2017 |
RTD0004541 |
ADA Operating Expense |
$1,371,830 |
2017 |
RTD0004542 |
Preventive Maintenance |
$3,054,810 |
2017 |
RTD0004552 |
Operating Assistance |
$1,257,050 |
2017 |
RTD0004550
|
Short Range Transit Planning |
$100,000 |
2017 |
RTD0004932
|
Replace 7 Model Yr 2004 Buses with new |
$2,989,000 |
2017 |
RTD0004919
|
Replace Parking Facilities Revenue Collection Equipment |
$300,000 |
2017 |
RTD0004989
|
Bus/ Van Mobile Location Project |
$300,000 |
2017 |
RTD0004540
|
Refurbish Engines on 8 Model Year 2011 Buses |
$280,000 |
2017 |
RTD0004990
|
Replace 1 Model Yr 2013 Support Vehicle |
$46,350 |
2018 |
RTD0005637 |
ADA Operating Expense |
$1,413,370 |
2018 |
RTD0005638 |
Preventive Maintenance |
$3,152,905 |
2018 |
RTD0005639 |
Refurbish Engine/ trans 8 model year 2012 buses |
$264,000 |
2018 |
RTD0005642 |
Operating Assistance |
$643,010 |
2018 |
RTD0005643 |
Short Range Transit Planning |
$100,000 |
2018 |
RTD0005656 |
Replace 6 Model Yr 2004 buses delivery 2018 |
$2,689,500 |
�
FFYs 2017 to 2021 MVMPO Transit Projects Funding (Cont.)
FFY Year |
Project Number |
Project Description |
Total Project Cost |
2018 |
RTD0005662 |
Replace 1 Model Yr 2013 Support Vehicle |
$47,750 |
2019 |
RTD0006769 |
Preventive Maintenance |
$3,250,095 |
2019 |
RTD0006770 |
ADA Operating Expense |
$1,456,420 |
2019 |
RTD0006771 |
Short Range Transit Planning |
$100,000 |
2019 |
RTD0006772 |
Operating Assistance |
$780,250 |
2019 |
RTD0007127 |
SGR Riverbank stabilization Design/Permitting |
$235,035 |
2019 |
RTD0007126 |
SGR Refurbish 4 vehicle lifts |
$400,000 |
2019 |
RTD0006785 |
Replace 1 Model Yr 2013 Support Vehicle |
$45,205 |
2020 |
RTD0007680 |
Preventive Maintenance |
$3,323,160 |
2020 |
RTD0007681 |
Non-Fixed Route ADA Para Serv |
$1,653,255 |
2020 |
RTD0007682 |
Short Range Transit Planning |
$100,000 |
2020 |
RTD0007683 |
Operating Assistance |
$861,550 |
2020 |
RTD0007687 |
Replace 3 Model Yr 2007 buses delivery 2020 |
$1,377,150 |
2020 |
RDT0007696 |
SGR Replace 1 Model Year 2013 supervisory vehicle |
$46,530 |
2020 |
RDT0008295 |
NEET Driving Forward 2020 |
$25,000 |
2020 |
RTD0008320 |
Town of Salisbury MAP Van for Svc Expansion (1) |
$68,000 |
FFYs 2017 to 2021 MVMPO Transit Projects Funding (Cont.)
FFY Year |
Project Number |
Project Description |
Total Project Cost |
2020 |
RTD0008311 |
Town of Andover MAP Buy Replacement Van (1) |
$69,100 |
2020 |
RTD0009193 |
Purchase On-board Automatic Passenger Counters (APC) |
$371,280 |
2021 |
RTD0008602 |
SGR Replace 1 model yr 2016 supervisory vehicle |
$47,900 |
2021 |
|
Replace Model Yr 2009 Buses Delivery 2022 (2 of 9) |
$990,674 |
2021 |
RTD0009132 |
SGR Replace Security Camera System at McGovern Center |
$131,000 |
2021 |
RTD0008595 |
Operating Assistance |
$1,116,240 |
2021 |
RTD0008592 |
Preventive Maintenance |
$3,495,970 |
2021 |
RTD0008594 |
Short Range Transit Planning |
$100,000 |
2021 |
RTD0008596 |
Replace 16 Model Yr 2015 vans with new Delivery 2021 |
$1,180,480 |
2021 |
RTD0008593 |
Non Fixed Route ADA Paratransit Service |
$1,741,065 |
2021 |
RTD0010047 |
SGR Replace 1 model yr 2016 Supervisory Vehicle |
$46,000 |
2021 |
RTD0010048 |
SGR Replace piping and related connections to underground gasoline tank |
$50,000 |
FFYs 2017 to 2021 MVMPO Transit Projects Funding (Cont.)
FFY Year |
Project Number |
Project Description |
Total Project Cost |
2021 |
RTD0010049 |
Purchase of new bus and van tires to replace used tires |
$65,000 |
2021 |
RTD0010050 |
Purchase licenses to upgrade diagnostic engine and transmission software |
$5,000 |
2021 |
RTD0010051 |
SGR Replace HVAC Unit in Money Room |
$6,938 |
2021 |
RTD0010305 |
Replace 2 servers/ related switches at MVRTA HQ |
$19,022 |
2021 |
RTD0010306 |
Replace Security Surveillance system at Gateway Parking Area |
$147,339 |
2021 |
RTD0010307 |
Replace Security Surveillance system at MVRTA Haverhill Intermodal Parking Facility |
$64,516 |
2021 |
RTD0010308 |
Purchase MDT units, camera and communication equipment for 9 ADA service vehicles |
$78,793 |
2021 |
RTD0010309 |
Upgrade security front gate entrance Control Pad at MVRTA HQ |
$2,500 |
2021 |
RTD0010310 |
Install Cloud Based data storage system at MVRTA HQ |
$12,891 |
2021 |
RTD0010311 |
Replace external security cameras on buses and vans |
$5,380 |
|
|
|
|
|
|
Total Transit Funding 2017 to 2021 |
$41,478,313 |